Where it stands
Paid $142,433 · Home not delivered · Contract terminated 13 October · Right to terminate disputed
Source catalogue
Evidence library
Find a source by subject, date or evidence ID, then open it with its citations. Choose Facebook posts or Google reviews for saved screenshots and replies. Calls includes Alex’s five conversation summaries and Kay’s signed account of Tim’s call to her.
More filters
- DOC-0113Facebook: Affordable Modular Buildings recommendationsThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- DOC-0112Facebook: contract terminationThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- COM-0089Expandify terminates the agreementExpandify says it will not deliver the home and intends to sell it to another party, retain payments against its claimed costs and resale losses, and refund any balance. No sale price, itemised deductions, refund amount or payment date is stated.
Provenance and limits
Actual termination notice at 10:08am; Kay’s solicitor disputes the right to terminate. Resale and any refund are proposed, not completed.
- DOC-0107Kay’s solicitor: warning before terminationKay’s solicitor warned on 12 October that Expandify still had no nominee, was seeking payment for work already paid for and/or site work not done, and had not remedied the breaches raised on 4 September. The letter said any purported termination would be treated as repudiation.
Provenance and limits
Kay’s solicitor warned on 12 October that Expandify still had no nominee, was seeking payment for work already paid for and/or site work not done, and had not remedied the breaches raised on 4 September. The letter said any purported termination would be treated as repudiation.
- DOC-0106Sixth QBCC company licence searchSix QBCC searches, from 11 August to 12 October, list the company licence as Active with no current nominee. These are dated snapshots, not proof of continuous absence between searches. The latest search records one structural direction not complied with, concerning an unidentified property; it is not linked to Kay’s project.
Provenance and limits
Six QBCC searches, from 11 August to 12 October, list the company licence as Active with no current nominee. These are dated snapshots, not proof of continuous absence between searches. The latest search records one structural direction not complied with, concerning an unidentified property; it is not linked to Kay’s project.
- DOC-0110Facebook: another day, still cricketsThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- DOC-0111Facebook: solicitor response updateThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- DOC-0105The Google review and owner repliesAlex’s review and two saved versions of Affordable Modular Buildings’ owner reply. Read each version in full.
Provenance and limits
Alex’s review and two saved versions of Affordable Modular Buildings’ owner reply. Read each version in full.
- DOC-0103The family’s solicitor: response to the cease-and-desist letterThe family’s response refuting the allegations and requesting further particulars.
Provenance and limits
Published correspondence; positions and allegations are attributed to the sender, not findings.
- COM-0088Expandify’s solicitors: public statements emailExpandify’s solicitors said the website and social media posts may contain defamatory imputations. They urged that the website be closed and public posts about the dispute stop, and said they would seek instructions before issuing a Concerns Notice.
Provenance and limits
These are their allegations and requests. This summary covers only the open public-statements email; no settlement terms are reproduced.
- COM-0087Expandify’s solicitors: further payment breach noticeExpandify’s solicitors adopted 18 September as the invoice issue date for this notice, while maintaining that an earlier dispatch had occurred. The notice demands payment of invoice 0278 for $67,200.91 by 12 October and says Expandify intends to terminate on 13 October if payment is not made.
Provenance and limits
The email sets out Expandify’s position and intended steps. It does not establish that the agreement has been terminated.
- DOC-0104Facebook: Affordable Modular Buildings review update and repliesThe full saved Affordable Modular Buildings review update, Tim’s comment, Alex’s reply and the accompanying discussion.
Provenance and limits
The full saved Affordable Modular Buildings review update, Tim’s comment, Alex’s reply and the accompanying discussion.
- DOC-0102Affordable Modular Buildings’ solicitors: cease-and-desist letterCease-and-desist letter demanding removal of publications.
Provenance and limits
Published correspondence; positions and allegations are attributed to the sender, not findings.
- DOC-0101Facebook: questions to ClaytonThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- DOC-0114Google: Alex’s Expandify reviewAlex’s review of Expandify, saved as seven original screenshots.
Provenance and limits
Alex’s review of Expandify, saved as seven original screenshots.
- DOC-0100QBCC company licence search: 28 September 2026The QBCC company search created on 28 September 2026 lists Expander Dwellings Pty Ltd with an active Builder – Open licence and no current nominee. It records one structural direction to rectify marked “not complied”. The 18 September search records the same count and category. The reports do not identify the property, defects or compliance deadline, or connect the direction to Kay’s project. They do not establish that the licence was suspended. Their separate “QBCC Disciplinary Action” field records none.
Provenance and limits
The QBCC company search created on 28 September 2026 lists Expander Dwellings Pty Ltd with an active Builder – Open licence and no current nominee. It records one structural direction to rectify marked “not complied”. The 18 September search records the same count and category. The reports do not identify the property, defects or compliance deadline, or connect the direction to Kay’s project. They do not establish that the licence was suspended. Their separate “QBCC Disciplinary Action” field records none.
- DOC-0109Facebook: original storyThe saved published post and accompanying comments, organised in reading order.
Provenance and limits
The saved published post and accompanying comments, organised in reading order.
- DOC-0096QBCC Company Licence Search: 18 SeptemberThe 18 September licence search records an active licence, no current nominees and one unmet structural direction, whose underlying details were not supplied.
Provenance and limits
Active licence and no current nominees at 15:25:34; page 4 records one structural direction not complied with. Underlying direction and property not supplied. Provenance: recovered from the native email attachment to the 18 September correspondence.
- DOC-0093Kay’s solicitor to Expandify’s lawyer: trust offer and termination disputeKay’s solicitor’s sent 18 September response records the trust proposal and termination dispute.
Provenance and limits
Redacted copy of Kay’s solicitor’s sent response only. The incoming email is summarised separately. Legal submissions and allegations are attributed to their sender, not findings.
- DOC-0091QBCC Company Licence Search: Active Licence No Current NomineesThe 16 September licence search records an active builder licence with no current nominees at that time, without establishing suspension or a continuous absence.
Provenance and limits
Six-page snapshot created 16 September 2026 at 17:12:20. Active Builder - Open licence 15556443; no current nominees. Does not prove suspension or continuous absence.
- COM-0086Expandify’s solicitor: direct-payment demand and termination warningSummary from the incoming 16 September email demanding direct payment and threatening termination.
Provenance and limits
Kay’s solicitor disputed the invoice history and entitlement to terminate. The screenshot is a sender-side record, not proof of receipt. This email threatens termination; it does not establish that termination occurred. This summary covers only the incoming 16 September communication.
- DOC-0092Xero INV-0278: Invoice Send History ScreenshotThe Xero screenshot records invoice sends and reminders to Kay, without establishing receipt or payment.
Provenance and limits
Supplied PNG; Xero history labelled AEST records send to Kay on 30 August 12:04, 1 September 12:51, 6 September 10:15 and reminder 13 September 06:15. Not proof of mailbox receipt or payment. Record-payment form is unsubmitted in this image.
- COM-0081Expandify notice of breachExpandify’s breach notice claims a 30 August invoice due date and a 14 September remedy deadline, which differ from its solicitor’s later dates.
Provenance and limits
Original notice asserts invoice due 30 August and calculates remedy deadline as 14 September; later lawyer gives different dates.
- DOC-0089QBCC Company Licence Search: Active Licence No Current NomineesThe 4 September licence search shows an active company licence with no current nominees at that time, without establishing how long that situation had lasted.
Provenance and limits
Both QBCC searches, dated 11 August and 4 September, show an active company licence and no current nominees. They are snapshots: they do not establish when the nominee ceased or a continuous period without one. The record does not establish insolvency or a suspended company licence.
- DOC-0088Kay’s solicitor to Expandify’s lawyer: notice to remedy breachKay’s solicitor’s notice sets deadlines for a nominee, installation and completion and warns of intended termination if they are missed; it does not itself terminate the contract.
Provenance and limits
The notice dated 4 September requires appointment and advice of a nominee within 14 days of the letter, installation to start by 21 September and practical completion by 16 October. It states an intention to terminate if the requirements are not met. It does not itself terminate the contract or establish a legal finding.
- COM-0085Kay’s solicitor to Expandify’s lawyer: sent response and breach notice coverKay’s solicitor’s sent 4 September response challenges Expandify’s contract, delay and payment positions and sends Kay’s breach notice.
Provenance and limits
Redacted copy of Kay’s solicitor’s sent response only. The incoming email is summarised separately. Legal submissions and allegations are attributed to their sender, not findings.
- COM-0084Expandify’s solicitor: contract position, delay explanation and proposed timetableSummary from the incoming 4 September email stating Expandify’s contract position, delay explanation and conditional timetable.
Provenance and limits
These were disputed positions, conditional delivery proposals and estimated installation and completion dates. Kay’s solicitor disputed the contract characterisation and delay explanation. The email says the replacement contract was sent in January; the reviewed replacement-contract documents are dated April. That discrepancy remains attributed to the sender.
- COM-0083Kay’s solicitor to Expandify’s lawyer: nominee, invoice timing and delayKay’s solicitor’s 3 September email requests nominee details and disputes the invoice timing, storage demand and delay explanation.
Provenance and limits
Kay’s solicitor's sent email of 3 September at 16:46 AEST requests the previous nominee's resignation date and replacement details by noon on 4 September. It disputes the early invoice and storage-cost demand, puts Kay's position that payment is due on 7 September, and challenges the delay explanation against the stated 20–29 week period. The quoted 1 September sending email is retained. The positions expressed are disputed legal submissions, not findings.
- DOC-0087Kay’s solicitor to Expandify’s lawyer: open letter on payment timing, nominee and completionKay’s solicitor’s open letter sets out her disputed position on payment timing and asks for nominee details and a completion schedule while recording delays and family impact.
Provenance and limits
Kay’s solicitor's revised open letter acknowledges foundation work and Expandify's report of port arrival on 30 August. It puts Kay's position that the next instalment is not due until 7 September, requests the previous and replacement nominee details and a completion program, and records delays and family impact. It contains no trust-payment offer. Legal allegations are the solicitor's position, not findings.
- DOC-0095INV-0278 Attached Invoice: Source ExtractThis transcription of the later invoice attachment records a changed due date of 30 August while retaining the earlier issue and expected-arrival dates.
Provenance and limits
Invoice transcription, not a facsimile of the original invoice. The attachment retains issue date 9 August, shows due date 30 August and expected arrival 21 August. It differs from the earlier 14 August due-date version.
- COM-0082Expandify’s solicitor: arrival, payment and proposed title transferSummary from the incoming 31 August email reporting arrival and proposing payment and title arrangements.
Provenance and limits
These were Expandify’s stated positions and a proposed amendment. The email does not establish lawful performance, acceptance of the proposal or transfer of ownership.
- COM-0080INV-0278 overdue reminderThe 31 August reminder states that the invoice was due on 30 August.
Provenance and limits
Native email dated 31 August states payment due 30 August. Separate from sender-side 30 August send history.
- COM-0079QBCC EDR case closureQBCC’s email confirms closure of the dispute-resolution matter without giving a reason or an outcome for the separate offence complaint.
Provenance and limits
QBCC confirms closure of the EDR matter on 28 August. Alex separately explains that she requested closure after Expandify engaged with the family. The email gives no reason for closure and no outcome on the separate offence complaint.
- COM-0078Foundation access and arrival updateExpandify’s update estimates five to eight hours for foundations and port arrival on 30 August, with further dates to follow quarantine release.
Provenance and limits
Five to eight hours estimated for foundations; port ETA 30 August; further dates after quarantine release.
- COM-0077Foundations booked for 31 AugustExpandify’s email books foundation installation for 31 August without confirming that the work was completed.
Provenance and limits
Foundation installation booking, not proof of completion.
- COM-0076Expandify ends Affordable Modular Buildings involvementExpandify’s notice says Affordable Modular Buildings is no longer involved and that communication and order management return to Expandify.
Provenance and limits
Formal notice that Affordable Modular Buildings is no longer involved and communication and order management return to Expandify.
- DOC-0084OOCL Tracking: Bill of Lading [cargo reference redacted]: Revised ETA 30 AugustThe carrier’s 18 August tracking record moves the Brisbane arrival estimate to 30 August; no notification of that change from either company is held.
Provenance and limits
Carrier tracking capture of 18 August 2026 for bill of lading [cargo reference redacted] showing the Brisbane estimate revised from 26 August to 30 August 2026 at 6:00am, with cargo available 10:00pm that night, aboard ALS LUNA 008S after transshipment at Qingdao. Obtained by Alex from the carrier's public tracking; the record holds no notification of the revised date from either company.
- COM-0075Expandify Xero overdue reminder for disputed INV-0278Expandify’s 16 August reminder marks the disputed $67,200.91 invoice overdue and warns of interest, although the displayed balance contains no interest charge.
Provenance and limits
Automated Xero reminder sent by Expandify Accounts to Kay at 6:15am on 16 August 2026, marking the disputed $67,200.91 invoice overdue, asking for payment as soon as possible and warning that bills more than seven days overdue will incur '12% interest charged daily'. The displayed balance does not include an interest amount.
- DOC-0008Kay’s solicitor to Tim Austin and ExpandifyKay’s solicitor’s 12 August letter addresses Tim directly, disputes the early payment demand and reserves Kay’s rights against him personally over the conduct alleged. It also requests authority, licensing, a work schedule and evidence of Expandify’s financial capacity.
Provenance and limits
Kay’s solicitor's 12 August letter disputing the arrival invoice and requesting evidence of authority, licensing, program and financial capacity.
- COM-0063Email the certifier to Alex: authority acknowledged and approved BA set suppliedThe certifier’s email acknowledges Alex’s authority to act and supplies the approved building documents directly to her.
Provenance and limits
The certifier’s email of 12 August 2026 acknowledging Alex's letter of authority and supplying the Approved BA Document Set directly to her; the certifier's independent release of the approval documents.
- COM-0058Email Expandify Xero reminder forwarded by Kay: INV-0278 due 14 AugustThe automated reminder keeps the disputed invoice’s 14 August due date after the payment demand was challenged.
Provenance and limits
Automated invoice reminder retaining the disputed 14 August due date after the payment demand had been challenged.
- Call 6 of 6Tim Austin says Affordable Modular Buildings is withdrawing from Expandify projectsAlex’s summary of the conversation. Statements remain attributed to the participants.
Provenance and limits
Tim announced Affordable Modular Buildings’ withdrawal. Alex challenged the early payment demand, the call to Kay and the pressure to withdraw regulatory and legal involvement.
- DOC-0108ASIC: current and former officeholders, August 2026Clayton Bielby is the current director in the 11 August extract. Sarah Kay Morrison and Lauren Zita Leidig are previous directors, with recorded cessation dates of 31 March 2026. Lauren’s secretary role also ceased on that date.
Provenance and limits
Dated officeholder record. Birth details and unrelated address/shareholder sections are excluded.
- DOC-0090QBCC Company Licence Search: Active Licence No Current NomineesThe 11 August licence search shows an active company licence with no current nominees at that time, without establishing how long that situation had lasted.
Provenance and limits
Both QBCC searches, dated 11 August and 4 September, show an active company licence and no current nominees. They are snapshots: they do not establish when the nominee ceased or a continuous period without one. The record does not establish insolvency or a suspended company licence.
- DOC-0072OOCL Tracking: Bill of Lading [cargo reference redacted]: ETA 26 AugustThe carrier’s tracking record shows departure from Qingdao and an estimated Brisbane arrival of 26 August.
Provenance and limits
Carrier bill of lading and tracking record showing departure from Qingdao and a Brisbane ETA of 26 August 2026 at 2:00 pm.
- Call 5 of 6Kay Power Signed First-Hand Account: Tim Austin CallKay’s signed account describes Tim Austin’s 11 August call and the emotional and health impact she reported.
Provenance and limits
Kay Power's signed first-hand account of Tim Austin's 11 August call and its reported emotional and health impact.
- COM-0057Email thread: Tim Affordable Modular Buildings urgent call request after payment disputeTim asks Alex to call him at 3:31pm. The quoted chain includes Alex’s unanswered questions, Affordable Modular Buildings’s acknowledgement and her earlier payment dispute and health instruction.
Provenance and limits
Tim’s 11 August 3:31pm request for Alex to call him, quoting her follow-up, Affordable Modular Buildings’ acknowledgement and the earlier payment dispute and health instruction.
- COM-0056Email thread: Tim Affordable Modular Buildings links continued involvement to payments and directionsTim Austin’s written follow-up links Affordable Modular Buildings’ continued involvement to payment and following its directions.
Provenance and limits
Written follow-up from Tim Austin linking Affordable Modular Buildings' continued project involvement to payment and compliance with its directions.
- COM-0055Email Affordable Modular Buildings Projects Team to Alex: acknowledges payment dispute and urgently refers response to TimAffordable Modular Buildings’ reply acknowledges Alex’s contact instruction and says it would be brought to Tim Austin’s attention.
Provenance and limits
11 August 2026 acknowledgement from Affordable Modular Buildings that Alex's communication instruction had been noted and would be brought to Tim Austin's attention.
- COM-0074QBCC EDR intake and process email: case [case reference redacted]QBCC’s intake email explains the dispute-resolution process, expected contact within four weeks and that participation does not automatically lead to an inspection.
Provenance and limits
QBCC intake email for EDR case [case reference redacted] explaining the process, an expected contact from a case officer within four weeks, and that participation does not automatically result in a building inspection.
- COM-0054Email Alex to Tim Affordable Modular Buildings: disputes premature payment demand and requests timelineAlex’s 10 August email disputes the invoice, asks for a work schedule and directs contact through her because of Kay’s cardiac investigations and stress.
Provenance and limits
10 August 2026 email disputing the invoice, requesting a program and directing communications through Alex because of Kay's cardiac investigations and stress.
- COM-0053Email Tim Affordable Modular Buildings: sends Expandify invoice and requests remittanceTim Austin’s 10 August email sends Expandify’s arrival invoice and asks for payment confirmation.
Provenance and limits
10 August 2026 email sending Expandify's arrival invoice and asking that remittance advice be provided to Tim Austin.
- COM-0052Email Alex to Tim Affordable Modular Buildings: explains EDR request and offers callAlex’s reply explains the dispute-resolution request and reproduces QBCC’s written timeframe and limits on the process.
Provenance and limits
Alex's 10 August response explaining the EDR position and reproducing QBCC's written four-week allocation timeframe and process limitations.
- COM-0051Email Tim Affordable Modular Buildings to Alex and Kay: queries QBCC EDR requestTim Austin’s 10 August email asks why Affordable Modular Buildings was included in the QBCC dispute-resolution matter.
Provenance and limits
10 August 2026 email in which Tim Austin queried why Affordable Modular Buildings had been included in the QBCC Early Dispute Resolution matter.
- DOC-0065Invoice INV-0278: Arrival Instalment: 67200.91: DISPUTEDThe disputed $67,200.91 arrival invoice asks for payment by 14 August while giving an expected arrival date of 21 August.
Provenance and limits
Disputed $67,200.91 Arrival in Port invoice dated 9 August 2026, due 14 August and recording an expected arrival of 21 August.
- DOC-0081Building approval decision and related forms: Publication extractA clearly labelled extract of the building approval decision, conditions and related forms. Approval is subject to conditions and referenced documents; this is not evidence of completion, compliance with every condition or final occupancy approval.
Provenance and limits
Decision Notice dated 6 August 2026, complete approval conditions and related forms. The publication extract retains original pages 1–18, 58–61 and 107–109, plus an explanatory cover. Technical drawings and other supporting material are omitted; the complete 152-page original is preserved privately. COM-0063 separately records transmission on 12 August 2026.
- COM-0050Email Tim Affordable Modular Buildings to Alex and Kay: building approval received: Project [project identifier redacted]Tim Austin’s 6 August email tells Kay and Alex that building approval had been received and no action was required.
Provenance and limits
Tim Austin's email of 6 August 2026 advising the certifier's Decision Notice of Approval had been received for project [project identifier redacted], stating no action was required and closing 'I bet you feel better now :)'; fixes the date the building approval was communicated to Kay and Alex.
- COM-0073QBCC offence complaint assessed for investigation: case [case reference redacted]QBCC’s notification refers the offence complaint to an investigator without making a finding that an offence occurred.
Provenance and limits
QBCC notification that offence complaint case [case reference redacted] had been assessed for investigation and referred to an investigator. It establishes the procedural status only; it is not a finding that an offence occurred.
Provenance and limits
Executed authority confirming Alex could act for Kay in project communications.
- COM-0064Email Tim Affordable Modular Buildings: project communication commitments and weekly updatesTim Austin’s July email sets out when clients would receive updates and cites Affordable Modular Buildings’ claimed delivery and approval record.
Provenance and limits
Tim Austin's bulk email of 29 July 2026 setting out Affordable Modular Buildings' communication policy (clients contacted only for approval, delays, scheduling and completion events) and citing '1200+ projects delivered in 5.5 years' with a '100% building approval success rate'.
- DOC-0071OOCL Tracking: Bill of Lading [cargo reference redacted]: ETA 26 AugustThe carrier’s 28 July tracking record shows the cargo’s route through Qingdao and an estimated Brisbane arrival of 26 August.
Provenance and limits
OOCL Control Tower tracking capture of 28 July 2026 for bill of lading [cargo reference redacted] (9 containers), showing departure from Xingang 16 July, discharge at Qingdao 20 July for transshipment, and ETA Brisbane 26 August 2026.
- COM-0049Email Tim Affordable Modular Buildings bcc all clients: potential crane and traffic management variationsTim Austin’s July email warns clients of possible installation cost changes for crane work requiring traffic management.
Provenance and limits
Tim Austin's bulk email of 22 July 2026 advising that crane companies now require professional traffic management where lifts affect roads or footpaths, foreshadowing potential installation cost variations for clients.
- COM-0048Email Tim Affordable Modular Buildings to Kay and Alex: project [project identifier redacted] on water, ETA 19 Aug, plumbing approved, building RFIThe 21 July update says the dwelling was on the water and plumbing approval had been obtained, while building approval remained under review.
Provenance and limits
21 July 2026 update stating the dwelling was on the water and plumbing approval had been obtained while building approval remained under review.
- COM-0047Email Tim Affordable Modular Buildings bcc all clients: onboarding delayed, individual updates next weekThe 16 July update says project information, approvals and history were being transferred into Affordable Modular Buildings’ system.
Provenance and limits
16 July 2026 update stating project information, approvals and history were being transferred into Affordable Modular Buildings' project-management system.
- DOC-0007Kay’s solicitor to Expandify: follow-up letterKay’s solicitor’s follow-up letter asks for a substantive written response to the issues raised on 30 June.
Provenance and limits
Kay’s solicitor follow-up requesting a substantive written response to the detailed 30 June letter.
- COM-0046Email thread: Expandify and Affordable Modular Buildings partnership announcement and follow-ups: full Gmail printThe partnership announcement thread introduces Affordable Modular Buildings and Tim Austin, repeats a claim of 1,200 delivered projects and preserves the follow-up emails.
Provenance and limits
Full Gmail print of the Affordable Modular Buildings partnership announcement thread, opening with Sarah's 1 July 2026 email introducing Affordable Modular Buildings, Tim Austin and a claimed 1,200 delivered projects, with the follow-ups that flowed from it.
- COM-0045Email trail Affordable Modular Buildings partnership announcement + Alex follow-ups to Tim (1: 9 Jul)The July thread records Alex following up on the promised call to Kay’s solicitor, foundations that had not started and missing approval updates.
Provenance and limits
Thread of 1 to 9 July 2026 in which Sarah redirects Alex to Tim Austin's address and Alex's 9 July follow-up records that the promised call to the solicitor had not happened, foundations had not started, and no approval status had been provided.
- COM-0044Email Tim (Affordable Modular Buildings) bcc all clients: intro, focus not on the pastThe 9 July introduction email announces that Expandify projects are moving into Affordable Modular Buildings’ system.
Provenance and limits
9 July 2026 Affordable Modular Buildings introduction and project-onboarding email announcing the transition of Expandify projects into Affordable Modular Buildings' system.
- Call 4 of 6Pressure to drop legal action, and the contract concessionAlex’s summary of the conversation. Statements remain attributed to the participants.
Provenance and limits
Five days after asking to meet Kay’s solicitor, Tim warned that pursuing legal action would hold up the project.
- COM-0043Email Expandify to Kay: rebooked shipping confirmation [cargo reference redacted] forwardedExpandify’s 8 July email forwards the rebooked shipping confirmation to Kay and Alex the day before the 9 July pressure call.
Provenance and limits
Expandify email of 8 July 2026 forwarding the freight forwarder's booking confirmation for [cargo reference redacted] (the rebooked shipping) to Kay and Alex; the shipping confirmation reaching the customer the day before the 9 July pressure call.
- DOC-0070Shipping Booking [cargo reference redacted] Revision 2: ETA 19 AugustThe third freight booking gives an estimated Brisbane arrival of 19 August 2026.
Provenance and limits
Freight forwarder's booking confirmation [cargo reference redacted] revision 2, dated 7 July 2026, now carrying ocean bill of lading [cargo reference redacted] with OOCL as carrier, ETD 7 July and ETA Brisbane 19 August 2026; the third booking revision.
- Call 3 of 6Affordable Modular Buildings partnership introducedAlex’s summary of the conversation. Statements remain attributed to the participants.
Provenance and limits
On this call Tim Austin asked to speak to the family's lawyer and discussed agreeing a scope of work with a proper contract.
- COM-0042Email thread Contract Concerns: payment table, ETA 8 Aug, spec sheet metadata challenge (15 Jun: 1 Jul)The Contract Concerns thread brings together the payment and timing explanations, the specification-sheet dispute and requests for earlier records.
Provenance and limits
Full print of the 'Contract Concerns' thread, 15 June to 1 July 2026, spanning the payment table and timeline defence, the specification sheet metadata challenge and pre-contract records requests, and ending with the certifier's request for the property owners' contact details.
- DOC-0006Kay’s solicitor to Expandify: letter of demandKay’s solicitor’s 30 June letter sets out her position on the disputed contract and payments and proposes safeguards for completion.
Provenance and limits
Kay’s solicitor's 30 June letter setting out Kay's legal position, disputed contract and payment issues, and proposed completion safeguards.
- COM-0041Email Sarah to Alex: spec sheet concession, that one is on me + cl 15.11 pivot (full thread 15-29 Jun)Sarah accepts that the supplied specification was the wrong template and relies instead on a contract clause.
Provenance and limits
The June email chain contains Sarah’s concession that the supplied specification was the wrong current template and her reliance on clause 15.11. The recovered Specification Sheet.pdf attachment is byte-identical to DOC-0009, the March 2025 brochure; that does not establish what Kay received before signing.
- COM-0040Email Alex to Sarah: metadata challenge + signed site placement form attached (thread 15-18 Jun)Alex’s June emails question the specification sheet’s date and contents and request the version said to have been supplied before the contract was signed.
Provenance and limits
Email chain to 18 June in which Alex challenges the supplied specification sheet's 2026 metadata and Home Warranty Insurance reference, compares the sender-side screenshot with Kay's received email, and requests the claimed pre-contract sheet and call records.
- COM-0039Email [the septic contractor] INV-1575 600 to Kay: Expandify advised invoice to you, they lodge plumbing application (+ Alex fwd re Clayton pay commitment)The septic contractor’s $600 invoice was issued to Kay and Alex, whose forwarded message says Clayton had indicated Expandify would pay it.
Provenance and limits
The septic contractor's invoice INV-1575 for $600, issued 17 June 2026 to Kay and Alex for the wastewater design and evaluation report 'prepared for Council submission', with Alex's same-day forward noting Clayton had indicated Expandify would pay it; the first and only invoice from the septic contractor located, and to whom it was issued.
Provenance and limits
Signed 16 June 2026 site-placement approval identifying the property owners and approved dwelling position.
- COM-0038Email trail [residential address redacted] to Contract Concerns: Clayton 15 Jun recap ETA 7 Aug + Alex fwds Site Placement form to Dana (23 May: 16 Jun)The email thread records revised shipping and foundation dates, Alex’s challenge to the timing of the plumbing application and the site-placement form sent for signature.
Provenance and limits
Thread of 23 May to 16 June 2026 containing Clayton's recap (booking attached, ETA 7 August; foundations booked for 9 July) and Sarah's reconciliation to an 8 August arrival with handover anticipated mid September, plus Alex's challenge that plumbing approval was 'only being lodged today'; also carries the site placement form forwarded to Dana and Marko for signature.
- COM-0037Email Sarah to Alex: booking rev1 attached + septic contractor chain 23-29 May (deep thread)Expandify’s revised June schedule gives August arrival and September handover estimates, with July foundation work dependent on approvals.
Provenance and limits
Sarah Morrison's written 16 June 2026 program revision recording an 8 August arrival, anticipated mid-September handover, foundations scheduled for 8 July and a foundations-team booking for 9 July dependent on approvals.
- DOC-0069Shipping Booking [cargo reference redacted] Revision 1: ETA 7 AugustThe revised freight booking moves the estimated Brisbane arrival to 7 August 2026.
Provenance and limits
Freight forwarder's booking confirmation [cargo reference redacted] revision 1, dated 15 June 2026, vessel GSL MELITA loading Tianjin, ETD 7 July and ETA Brisbane 7 August 2026; records the first slip of the booked window.
- COM-0036Email Sarah to Alex: Contract Concerns, payment table and foundation timingSarah’s written follow-up addresses conflicting payment terms and proposed construction timing before signing.
Provenance and limits
Sarah's written follow-up after the Clayton call, addressing conflicting payment terms and proposed construction timing before signing
- Call 2 of 6Shipping cause, overpayment and contract concernsAlex’s summary of the conversation. Statements remain attributed to the participants.
Provenance and limits
Clayton described Expandify as new to the industry while discussing shipping, payments and the replacement contract.
- COM-0035Email Clayton call booking + Kirsty 29 May Expandify will complete plumbing permit submission ([the septic contractor] trail)The email thread records Expandify saying it would submit the plumbing permit application while arranging Clayton’s call with Alex.
Provenance and limits
Thread of 29 May to 5 June 2026 booking Clayton's Monday call with Alex, retaining Kirsty-Lea Savage's 29 May line 'Expandify will be completing the plumbing permit submission'; fixes in writing who was to lodge the plumbing application.
- DOC-00732026: QBCC Licence Record: Expander Dwellings: 15556443The QBCC record gives 7 January 2026 as the start date of Expander Dwellings’ builder licence.
Provenance and limits
QBCC licence record showing Expander Dwellings Pty Ltd's builder licence commenced on 7 January 2026.
- COM-0034Email trail between Kirsty and the septic contractor: Expandify managing septic assessment (15 Apr: 1 Jun)The septic contractor’s email trail records Expandify’s follow-ups and the timing of the wastewater-design work from April to June.
Provenance and limits
Full email trail with the septic contractor showing Expandify's follow-ups from April to June 2026 and the documented timing of the wastewater-design work.
- COM-0033Email Sarah-Kay: hold-up is on our end, all six homes still in ChinaExpandify’s June email says all six homes in Kay’s batch were still in China and acknowledges her earlier warning about health-related stress.
Provenance and limits
1 June 2026 email stating all six homes in Kay's batch remained in China and acknowledging Kay's earlier written warning about health-related stress.
Provenance and limits
The septic contractor's final wastewater design for the site (project [project identifier redacted]) showing the existing [septic-system supplier] 1,500L system against a calculated 1,350L per day requirement, with land application area calculations for the proposed two bedroom dwelling, as at 29 May 2026.
- COM-0032Email from the septic contractor to Alex: final wastewater design deliveredThe septic contractor’s covering email records the final wastewater design reaching Alex on 29 May.
Provenance and limits
The septic contractor's covering email of 29 May 2026 delivering the final wastewater design ('FINAL V1', the septic contractor's wastewater design dated 29.05.2026); fixes the date the completed design reached Alex.
- COM-0031Email Alex to Expandify: challenges [the septic contractor] invoice narrative (subset trail)Alex’s May email challenges the claim that an outstanding septic contractor invoice was delaying the project; no such invoice is held.
Provenance and limits
29 May 2026 email challenging the claim that an outstanding invoice from the septic contractor was holding up the project; no such invoice is in the record.
- COM-0030Email trail Update on Shipping FULL (27 Apr-22 May): incl Clayton 18 May spec sheet claim + always-required contract admissionThe shipping email thread preserves Expandify’s claims about the specification sheet, an unpaid septic report and the need for a separate contract for installation.
Provenance and limits
Full Gmail print of the 'Update on Shipping' thread, 27 April to 22 May 2026, retaining Sarah's statements that the attached specification sheet is 'the correct specification sheet from that time', that the septic contractor's inspector 'had not been paid' for the formal report, and that a QBCC contract 'was always required to cover the on-site installation phase'.
- COM-0029Email trail Alex-Clayton-Sarah: QBCC complaint threat, delay admissions (27 Apr: 22 May)Alex’s May email challenges the form naming Kay as property owner and passes on the septic contractor’s account of unanswered invoice follow-ups to Expandify.
Provenance and limits
Alex's email of 22 May 2026 telling Sarah and Clayton that the Form 18 wrongly names Kay as property owner (the owners are Kay’s daughter and son-in-law) and that the septic contractor say their invoice went to Expandify with follow-ups unanswered; both corrections put to the company in writing.
- COM-0027Email the certifier to Kay: Form 18 issued (wrongly names Kay as owner)The certifier’s May engagement email incorrectly names Kay as the property owner.
Provenance and limits
19 May 2026 Form 18 engagement email from the private certifier that incorrectly identified Kay as the property owner.
- DOC-0027Specification Sheet v1.2: Original PDF Metadata PreservedThis specification supplied in May 2026 is part of the dispute over which specifications applied before the contract was signed.
Provenance and limits
Historical specification PDF supplied in May 2026 whose metadata and provenance became part of the disputed pre-contract scope record.
- COM-0026Email trail Clayton-Alex: shipping + septic council capacity questions (27-29 Apr)The April email exchange records Clayton’s explanation of certification paperwork and Alex’s questions about septic approval and when the tank information reached council.
Provenance and limits
Email trail of 27 to 29 April 2026 in which Clayton explains the Form 15 certification paperwork and Alex presses for the septic status with council and asks when the tank information was first submitted.
- COM-0025CRM screenshot from Clayton: Sarah SMS 9 Jun 2025 tank adequate (p1 of 2)The message screenshot records Sarah’s second-hand reassurance about the septic tank while the official report was outstanding, alongside an invoice offer Kay accepted.
Provenance and limits
CRM screenshot provided by Clayton showing Sarah's SMS to Kay of 9 June 2025, giving a second-hand tank reassurance ('I have spoken to [the septic contractor] and he sees no reason why your tank would not meet the purposes') while the official report was outstanding and offering the $6,300 invoice in the same message; Kay accepted eight minutes later.
- DOC-0068Shipping Booking [cargo reference redacted] Revision 0: ETA 14 JuneThe first freight booking gives an estimated Brisbane arrival of 14 June 2026.
Provenance and limits
Freight forwarder's sea freight booking confirmation [cargo reference redacted] revision 0, dated 27 April 2026, consignee Kay Power, goods 'PEAK - 1 X 40'OT + 1 X 20GP', ETD 13 May and ETA Brisbane 14 June 2026; the first of three booking revisions.
- COM-0023Email Clayton to Kay: booking [cargo reference redacted] sent, ETA Brisbane 14 JunExpandify’s April email forwards a freight booking with an estimated Brisbane arrival of 14 June.
Provenance and limits
27 April 2026 freight booking forwarded by Expandify with a then-current 14 June Brisbane ETA.
- DOC-0003Replacement QBCC Contract v2: 97 Days: UNSIGNEDThe second unsigned replacement contract shortens the proposed completion period to 97 days after the original period was questioned.
Provenance and limits
Second unsigned version of the replacement QBCC-format contract pack, reissued a week after version 1; the revision whose completion period was shortened to 97 days after the original period was questioned.
- COM-0022Email Expandify: RE update on your shipment and next stepsExpandify’s April reply addresses the approval process, septic questions and shipping records and says the 241-day contract period would be corrected.
Provenance and limits
Sarah Morrison's numbered reply of 14 April 2026: complying development applies with council questioning the septic system, files sit in Buildertrend, the private certifier is identified, the 241 day period 'was set at the standard approx timeline' and would be corrected, and booking details were re-attached.
- Call 1 of 6Approvals, septic risk and shipping delaysAlex’s summary of the conversation. Statements remain attributed to the participants.
Provenance and limits
Sarah accepted Alex’s concern that the project had exceeded Expandify’s stated maximum timeline.
- DOC-0078QHWS Tax Invoice: Premium 1225.80 PaidQBCC’s tax invoice records receipt of the $1,225.80 home warranty premium from Expander Dwellings.
Provenance and limits
QBCC tax invoice for policy [insurance policy redacted] dated 9 April 2026 showing the $1,225.80 QHWS premium received from Expander Dwellings Pty Ltd, licence 15556443; fixes when the statutory premium was paid.
- DOC-0077QHWS Homeowner Cover Letter: Policy [insurance policy redacted]QBCC’s 9 April letter tells Kay that the construction work is covered by the Queensland Home Warranty Scheme.
Provenance and limits
QBCC letter to Kay dated 9 April 2026 confirming the construction work at [residential address redacted] is covered by the Queensland Home Warranty Scheme under policy [insurance policy redacted], with instructions to check the notice of cover.
- DOC-0076QHWS Notice of Cover: Policy [insurance policy redacted]The Home Warranty Scheme notice records when the cover was issued and commenced.
Provenance and limits
QHWS issue and commencement dates
Provenance and limits
ASIC current and historical company extract showing Clayton Bielby was appointed a director of Expander Dwellings Pty Ltd on 1 May 2025; Sarah Morrison is a director; Lauren Zita Leidig is a director and secretary.
- COM-0071Email QBCC to Kay: QHWS cover issued with policy documentsQBCC’s April email confirms home warranty cover and offers Kay the option to increase the maximum compensation.
Provenance and limits
QBCC email to Kay of 9 April 2026 confirming QHWS cover for the project with the notice of cover attached, including the option to increase maximum compensation from $200,000 to $300,000.
- COM-0020Email Alex to Sarah: five information requests re approvals and shippingAlex’s April email asks for approval details, paid-for reports, the certifier’s identity, an explanation of the completion period and shipping documents.
Provenance and limits
Alex's email to Sarah Morrison of 9 April 2026 making five information requests: the approval pathway and status, copies of the paid-for reports, the certifier's identity, an explanation of the 241 day completion period, and shipping documentation.
- DOC-0002Replacement QBCC Contract v1: 241 Days: UNSIGNEDThe first unsigned replacement contract proposes a 241-day completion period in place of the 2025 sales agreement.
Provenance and limits
Unsigned QBCC-format Expandify New Home Construction Contract pack, version 1 (Consumer Building Guide, general conditions and schedules), sent as the proposed replacement for the 2025 sales agreement; the version whose schedule the solicitor's letter records as carrying a 241 day completion period.
- COM-0019Email Sarah to Kay: delay + new QBCC contract demand + 26880.36 acceleration offerExpandify’s April email presents a 241-day replacement contract, a $26,880.36 acceleration option and its explanation for shipping delays.
Provenance and limits
April 2026 email presenting a 241-day replacement contract, an additional $26,880.36 acceleration option and the company's shipping-delay explanation.
- COM-0018Letter OOCL: departure rescheduled to 13 Apr (authenticity unverified)The unverified letter on carrier letterhead is kept as a record of the shipping-delay explanation Expandify supplied to Kay.
Provenance and limits
Letter on OOCL letterhead dated 27 March 2026 citing staff availability and reduced 'fuel security' and rescheduling departure to 13 April aboard 'NTX A3N'; provided to Kay via Expandify, provenance unverified, preserved as a record of what she was given.
- COM-0017Email Expandify Admin to Kay: ETD 27 Mar, install 4 May, handover 30 MayExpandify’s March email sets out a proposed schedule from departure in China through installation to handover on 30 May.
Provenance and limits
Expandify email of 12 March 2026 setting a full written program: ship departs China 27 March, install 4 to 15 May, trades and inspections to 29 May, proposed handover 30 May 2026.
- DOC-00242026-02: Specification Sheet v1.3: Signature PackageThis later Signature Package specification is kept for comparison with the specification said to apply before Kay signed.
Provenance and limits
Post-contract Signature Package specification created in January 2026 and retained for comparison with the specification said to apply before Kay signed in July 2025.
- COM-0016Email Clayton to Kay: apology for wrong name and delays (Kay in one bedroom since Jul 2025)The January correspondence records Kay’s displaced living situation and an apology for addressing her by the wrong name.
Provenance and limits
January 2026 correspondence recording Kay's displaced living situation and an apology after she was addressed by the wrong name.
- COM-0015Email Expandify Admin to Kay (Dear Deborah): home complete, installer terminated, ETA Mar-AprThe 20 January email is the first held express statement from Expandify that Kay’s home is complete, alongside news of a shipping delay and a change of installer.
Provenance and limits
Expandify email of 20 January 2026, addressed 'Hello Deborah', stating the home is complete, shipping will slip to a late March arrival, and the installation contractor has been terminated on quality grounds with a new team to be trained. This is the first held express statement from Expandify that the home is complete.
- COM-0014Email Expandify Sales to Kay: vessel failed to load pre-ChristmasExpandify’s January email explains that the allocated vessel did not load before Christmas and says Chinese New Year would further limit shipping schedules.
Provenance and limits
Expandify email of 16 January 2026 advising the allocated vessel could not load before the Christmas shutdown, that the buildings must travel on top of the ship with nothing loaded above them, and that Chinese New Year would further constrain schedules.
- COM-0013Email Expandify bulk: QBCC licence announced, new 224k pricing, pre-compliance checks for new customersExpandify’s January email announces its QBCC licence, new pricing and a pre-compliance check for new customers.
Provenance and limits
Expandify bulk 'Happy New Year' email of 16 January 2026 announcing the QBCC licence (number 15556443), introductory January 2026 pricing and a complimentary pre-compliance check for new customers; the company's own framing of 2025 and the licence announcement to its client base.
- DOC-00672026: Expandify Portal Build Photos and Payment CommentThe portal screenshot records payments, factory-work updates and Kay’s selections, although the displayed dates may be upload dates rather than the dates the photos were taken.
Provenance and limits
Screenshot of Kay's Buildertrend project dashboard showing a displayed price of $232,034.20, total paid $142,433.02, the first held dated portal update on 11 November 2025, visible external factory work on 3 December and internal fit-out with hanging electrical wiring on 14 January 2026. The displayed price reconciles exactly to the $224,003 signed price plus $8,031.20 in paid preliminary invoices, but the record does not explain the portal label. Portal dates may be upload dates rather than camera-capture dates. It also records Kay's 23 October 2025 payment note and dishwasher-to-cupboard selection.
- DOC-00662026: Expandify Portal Invoice Ledger ScreenshotThe portal ledger lists five paid invoices totalling $142,433.02 and labels the contract price plus preliminary payments as the original price, without explaining that label.
Provenance and limits
Screenshot of the Buildertrend invoice ledger for project [project identifier redacted] showing an original price of $232,034.20, five paid invoices totalling $142,433.02 and a stated remaining balance of $89,601.18. The portal figure reconciles exactly to the $224,003 signed price plus $8,031.20 in paid preliminary invoices. The record does not explain why the portal labels that combined amount as the original price.
- COM-0012Portal messages Sarah-Kay: stumps 1-2 wks pre-delivery, ETA late Jan-FebThe December messages give hoped-for shipping and arrival dates and say foundations would be installed one to two weeks before delivery.
Provenance and limits
December record of hoped-for pre-shutdown sailing, late-January or early-February port arrival and foundations one to two weeks before site delivery
- COM-0011Email Expandify bulk: delays acknowledged, display home pausedExpandify’s December email acknowledges delays and says it is pausing the display-home installation to prioritise existing customers’ builds.
Provenance and limits
Expandify bulk email of 1 December 2025 acknowledging things have 'moved a little slower than planned' and announcing the Raceview display home installation pause to prioritise existing client builds.
- DOC-0064Invoice 0006: 30 Percent Build Complete: 67200.91The paid $67,200.91 Build Complete invoice brought contract payments to 60 per cent even though its description said the build was only “almost ready” for inspection.
Provenance and limits
Paid second 30 per cent Build Complete invoice for $67,200.91, due 21 October and paid 22 October 2025. Together with the deposit, contract instalments paid reached 60 per cent. Its description says the build is only 'almost ready' and will undergo inspection that week. It allocates amounts within the invoice total to foundation, installation, crane, delivery and certification components.
- COM-0010Portal messages: frame complete, ETA Jan-Feb 2026, Kay timeline pushbackThe October portal exchange lists work still underway, links forthcoming factory photos to the next invoice and records Kay’s questions about the timing estimates.
Provenance and limits
October 2025 portal exchange saying only the frame and structure are complete, listing lining preparation, electrical planning, fixtures, final assembly and quality testing as still underway, and promising factory images in about three weeks to trigger the next invoice. It also records a 20-to-24-week batch turnaround, 19 December port estimate, end-January or early-February completion estimate and Kay's earlier timing expectations.
- DOC-0063Invoice 0005: 30 Percent Deposit: 67200.91The paid $67,200.91 deposit invoice lists the project scope without separate prices for its individual components.
Provenance and limits
Paid 30 per cent deposit invoice for $67,200.91 issued immediately after the sales agreement was signed. It lists the complete project scope but does not allocate separate prices to the individual components.
- DOC-0001Signed Sales Agreement: Peak Complete Package: 224003Kay’s signed $224,003 sales agreement sets out the payment stages, defines when the build is complete and leaves the anticipated delivery date blank.
Provenance and limits
Executed $224,003 sales agreement recording the contracting party, 30/30/30/10 payment schedule, incomplete Schedule 1 fields and the blank anticipated delivery date. It makes the second 30 per cent payable upon Build Complete and defines Build Complete as the date manufacture of the goods is complete.
- COM-0069Email Kay reply to proposal: approved signed and requests split deposit around house settlementKay’s July email records her signing and her plan to pay the deposit balance from her house settlement.
Provenance and limits
11 July 2025 email recording Kay's signing and her plan to fund the balance of the deposit from her house settlement.
- COM-0068Buildertrend invoice notice: 30 percent deposit 67200.91 due same dayThe deposit notice issues the $67,200.91 invoice on the day Kay signed and makes it due that same night.
Provenance and limits
Buildertrend notice of 11 July 2025, 5:24pm, issuing the $67,200.91 30 per cent deposit invoice with a due time of 11:59pm the same day; evidences the deposit was invoiced and due on the day of signing.
Provenance and limits
20 June 2025 soil test recording the site's classification and geotechnical information for the proposed works.
Provenance and limits
Completed 20 June 2025 site survey documenting early site investigation work before physical construction.
- DOC-0062Invoice 0004: Site Assessment: 6560The $6,560 site-assessment invoice lists the survey, testing, drafting and engineering charges covered by the third preliminary payment.
Provenance and limits
Buildertrend invoice 100-[project identifier redacted]-0004 for the $6,560 site assessment, itemising site survey, soil test, wind rating, drafting, engineering and an over-2000m2 charge, paid 9 June 2025; the third preliminary payment.
- DOC-0061Invoice 0002: BAL Report: 871.20The $871.20 BAL-report invoice records the second preliminary payment.
Provenance and limits
Buildertrend invoice 100-[project identifier redacted]-0002 for the $871.20 BAL report under 'Council and Building Certification', paid 28 May 2025; the second preliminary payment.
- COM-0008Email Logan Council RFI [case reference redacted]: septic records refused to Expandify (with internal Sarah-Lauren chain)Expandify’s email asks Kay or her daughter to obtain septic records after council declined to release them to the company.
Provenance and limits
Email of 19 May 2025 in which Lauren Zita tells Kay that Logan City Council will not release the registered septic records to Expandify and asks her to obtain them herself or through her daughter, with the internal Sarah-Lauren chain beneath; council refused the company the records and the task moved to the customer.
- COM-0005Screenshot Lauren-Kay thread: spec sheet listed but Kay reported no attachments, re-send lacked it (captured 17 Jun 2026)Expandify’s mailbox screenshot lists a specification sheet among the attachments in the thread where Kay reported receiving none.
Provenance and limits
Outlook screenshot captured 17 June 2026 of the 16 May 2025 8:44pm re-send, showing its attachment list as the Ridge and Nova floor plan images plus a 'Specification Sheet.pdf' (116 KB), within the thread where Kay had reported no attachments; records what Expandify's mailbox shows as attached to that email.
- COM-0003Email Lauren re-send to Kay: Ridge + Nova JPEGs ONLY, no spec sheet attachedExpandify’s email resends attachments after Kay reported that nothing was attached.
Provenance and limits
Lauren Zita's re-send of 16 May 2025 8:44pm asking 'Did these attachments work for you?' after Kay's reply 'Hi Nothing is attached'; the re-send that followed the reported attachment failure.
- COM-0002Email Kay to Lauren: Nothing is attached (non-receipt in writing, thread to 19 May incl BAL-septic report line)The email thread records Kay reporting missing attachments and Expandify advising that BAL and septic reports were needed before site assessments.
Provenance and limits
Printed Gmail thread of 16 to 19 May 2025 in which Kay reports non-receipt of attachments and Lauren Zita advises the BAL and septic reports are required before site assessments, with invoices to follow once tradespeople are confirmed.
- COM-0001Email Kay: query on 600 feasibility invoice (issued 6 May)Kay’s email asks about the feasibility report ten days after she paid for it and before she had received it.
Provenance and limits
Kay's email of 16 May 2025 chasing the $600 feasibility invoice issued and paid 6 May ('just wondering if this has been done yet?'); evidences that ten days after paying she had not received the report.
- DOC-0012Preliminary Assessment Report: Onsite Sewerage IssuesThe certifier’s May assessment records the need for building and septic approvals and the lack of a mains sewer connection before the contract was signed.
Provenance and limits
Private certifier's Preliminary Assessment Report of 8 May 2025 recording that the project requires both Building Approval and Septic System Approval and noting the property is not connected to the main sewer, nine weeks before the contract was signed.
- DOC-0060Invoice 0001: Preliminary Site Feasibility: 600The $600 feasibility-report invoice records the first payment on the project.
Provenance and limits
Buildertrend invoice 100-[project identifier redacted]-0001 for the $600 Preliminary Site Feasibility Report, issued 6 May 2025 and paid the same day via Xero; the first payment on the project.
- DOC-0009Expandify Pre-Contract Brochure Sent to KayExpandify’s pre-contract brochure describes the build, shipping, installation and approval process, including its stated build times and licensed installation team.
Provenance and limits
Pre-contract brochure describing build, shipping, installation and council-approval steps, including the stated 45-day build cycles (build and certification typically around 8 weeks) and QBCC-licensed installation team. The recovered Specification Sheet.pdf attached to Sarah’s 29 June 2026 email is byte-identical to this 16-page brochure (SHA-256 c070aa041a2739bab4038fa0fa7f785148d3a78aab91ffae91038a742397aad7). It contains no septic or wastewater wording and refers to a separate specification sheet. Identity of the recovered file does not establish attachment to Kay’s 16 May 2025 received email.
- DOC-0010UNDATED: Expandify Construction Journey Brochure: Maximum 29 WeeksExpandify’s Construction Journey guide, sent after the contract was signed, gives its own estimate of 20 to 29 weeks for the overall process.
Provenance and limits
Construction Journey guide recording an approximate overall process of 20 to 29 weeks; sent after contract and used only as the company's own timing guide.