Evidence library · COM-0038

Email trail [residential address redacted] to Contract Concerns: Clayton 15 Jun recap ETA 7 Aug + Alex fwds Site Placement form to Dana (23 May: 16 Jun)

Source date: 16 June 2026 · Email thread print

The email thread records revised shipping and foundation dates, Alex’s challenge to the timing of the plumbing application and the site-placement form sent for signature.

Thread of 23 May to 16 June 2026 containing Clayton's recap (booking attached, ETA 7 August; foundations booked for 9 July) and Sarah's reconciliation to an 8 August arrival with handover anticipated mid September, plus Alex's challenge that plumbing approval was 'only being lodged today'; also carries the site placement form forwarded to Dana and Marko for signature.

Source limitations

Publication copy with third-party identifying details redacted. The complete original is preserved privately.