Paid $142,433 · Home not delivered · Contract terminated 13 October · Right to terminate disputed
The record
The full chronology
The dated record now runs through Expandify’s termination notice on 13 October 2026, including the 12 October QBCC search and Kay’s solicitor’s warning. The entries distinguish forecasts, missed commitments, actual progress and disputed accounts. Documentary sources are linked; additional conversation accounts are identified in the relevant entries. Written evidence and attributed accounts are distinguished throughout.
OrderFollow the whole story.
99 dated events ·
Before the contract: March to July 2025
Before the contract: the report that named both approvals, and the reassurance that arrived with an invoice.
Pre-contract
DeliveryApprovalsRegulator
Pre-contract brochure: listed date. The record lists 20 March 2025 for this brochure. Its contents are verified; the original email establishing when it was sent to Kay is not in the record.
Build: 45-day build cycles, with build and certification typically around 8 weeks.
Shipping: four to five weeks.
Installation: one to three weeks.
Council: handled "from start to finish, including... handling the submission on your behalf".
Customer promise: "transparency in our processes, pricing, and timelines".
Pre-contract
MoneyDelivery
First invoice: $600 for a Preliminary Site Feasibility Report. Kay pays it.
Pre-contract
DeliveryApprovals
The private certifier's Preliminary Assessment Report, obtained by Expandify, records two required approvals:
Building approval: yes.
Septic system approval: yes - "Not connected to the main sewer".
Pre-contract
Approvals
On Expandify's later account:
A conference call takes place between Kay and two staff members, in which septic is said to have been put outside scope.
Expandify says a specification sheet was emailed to Kay that day. The version produced in 2026 carried a creation date of 18 May 2026.
Contemporaneous attachment records: Kay writes “Nothing is attached”. The received resend lists two JPEGs; a sender-side screenshot lists a specification-sheet attachment as well. These records differ and do not establish that Kay received the sheet relied on in 2026.
Pre-contract
Approvals
Septic requirements and access to council records. Lauren tells Kay that BAL and septic reports are required before the site assessments. Council declines to release septic records to Expandify because it is not the property owner. Sarah asks the team to obtain the records through Kay and the family, and Lauren passes on that request.
This records both early awareness of the septic requirements and an attempt to obtain the information.
Pre-contract
MoneyDelivery
Second invoice: $871.20 for a bushfire (BAL) report. Paid.
Pre-contract
Money
Sarah Morrison, by SMS: "I have spoken to [the septic contractor] and he sees no reason why your tank would not meet the purposes for adding the additional dwelling... This stage is the $6,300. I can arrange for this invoice to be sent today if you are ready to take those next steps."
The septic contractor: an external plumbing contractor consulted on the tank.
Payment: the $6,560 site-assessment invoice is paid the same day.
Pre-contract
Site survey and soil test carried out.
The contract: July 2025
The contract: six blank schedule fields, a payment clock and no anticipated delivery date.
WK 0
MoneyDeliveryApprovalsHealth
Mum’s expectation at sale: Kay expected the home to ship in December 2025 and be installed in January 2026. This is the family’s account, clarified by Alex, of the timing Mum expected when she bought the home. The signed agreement’s Anticipated Delivery Date field was blank.
Kay signs the Sales Agreement:
Package: The Peak Complete Supply, Install and Council Approval Package - "the dwelling, complying development council approvals, installation, and everything in between" - $224,003.00.
Incomplete particulars: six of eleven. Purchase Price and Description of Goods retain $###### placeholders; Exchange Rate, Anticipated Delivery Date, Delivery Address and Special Conditions are blank.
Refund clause: clause 7.9, the only clause returning all money paid, is calculated from the blank Anticipated Delivery Date.
Security: clause 14.2 charges Kay's present and after-acquired property in Expandify's favour; clause 14.3 consents to a caveat.
Kay writes the same day: "Have approved and signed. Can I pay $45000 now and rest of the 30% on my house settlement, which should be the 1 August 2025". The record shows from day one that the deposit is funded by the sale of her house.
WK 0
MoneyApprovalsRegulator
Deposit records: the invoice is dated 12 July; the notice in Expandify’s customer portal, Buildertrend, is dated 11 July and requests $67,200.91, due that day. The deposit was subsequently paid; the notice and invoice dates do not establish when each payment cleared. Kay had requested a split payment on 11 July.
Licence position: Expandify holds no QBCC builder licence at this point. Its licence commences 7 January 2026.
Manufacture and the first slip: October to December 2025
The first slip: 60 per cent paid while the invoice said ‘almost ready’; later records show factory work continuing.
WK 12
MoneyDelivery
Status given: Expandify says the frame and structure are complete.
Work still underway: lining preparation and internal framework checks, electrical layout planning, materials and fixtures being prepared for fit-out, and factory quality checks. Final assembly and comprehensive quality testing are described as later steps.
Arrival forecast: the batch is expected to arrive at port around January/February 2026, depending on the factory schedule, shipping allocation and quarantine clearance. This is a port-arrival estimate, not an installation date.
Next payment: "In approx 3 weeks you will receive images and videos of the build in factory. This will trigger your next invoice payment."
Arrival payment: the invoice "will be issued with the due date approx 1 week prior to port arrival".
Guide supplied: the same email thread attaches the Construction Journey Guide. It gives approximately 20–29 weeks overall, allowing for scheduling, port delays and site conditions. This is guidance supplied after signing, not a completion date inserted into the signed contract.
WK 12
Delivery
The timeline slips again in an email exchange.
Kay Power: "When I first talked about it, i was told 20 wks. Then, when signed, I was told hopefully finished by Christmas, and now it is not arriving to Jan/Feb."
Sarah Morrison, replying the same morning: the batch closed 25 July with a 20 to 24 week turnaround, "an approximate arrival into port date of the 19th of December if we went with the lower 20 weeks", and, in the same email, "the port and trucks do shut down from the 15th of December meaning the orders won't be able to land at port untill the new year".
In that same email, Expandify gave 19 December as the best-case arrival and said the port would shut from 15 December.
Completion estimate in Sarah’s reply: end of January or early February. This is separate from the 7 October email’s January/February port-arrival estimate. Kay’s quoted recollection above is retained alongside the family’s clarification that she expected December shipment and January installation when she bought the home.
WK 14
MoneyDeliveryApprovals
Contract milestone: the second 30 per cent is payable at Build Complete, defined as the date manufacture is complete.
Invoice: $67,200.91, due 21 October and paid 22 October. Together with the deposit, this brought contract instalments paid to 60 per cent, or $134,401.82.
Description: titled "30% Build Complete", but says: "Your Build is almost ready in factory and will be going through inspection this week".
Scope and allocations: both paid invoices list the complete project scope. The October invoice allocates amounts within its 30 per cent total to foundation install, building install, installation management, crane hire, delivery from port, cleaning and the certifier's final sign-off visit. These allocations do not establish that those components were separately paid in full.
Ninety days to written completion confirmation: on 20 January 2026, Expandify states, “Your home has been completed.” That is 90 days after the payment; it does not establish the exact date manufacture was completed.
WK 17
MoneyDelivery
11 November: first dated portal update in the record.
3 December: the update visibly shows external factory work continuing.
Date caution: portal dates may be upload dates rather than camera-capture dates; they do not establish the exact day the photographs were taken.
WK 20
Delivery
Bulk email: delays acknowledged, the Raceview display home installation is paused, "keeping our promises and caring for our customers comes first, always".
WK 22
Delivery
Hoping to ship before the holiday shutdown. Sarah says the factory is packing the batch: “We are hoping they can get them on the water before the holiday shut down but it might be after.” Port arrival is forecast for late January to early February; stumps are to go in one to two weeks before site delivery.
The 16 January update later confirms that loading before the Christmas shutdown did not happen.
The explanations: January to June 2026
Shipping delays, the wastewater approval process and requests for the records behind the company’s explanations.
WK 25
DeliveryApprovalsRegulator
The licence record shows Expander Dwellings Pty Ltd’s builder licence commenced on 7 January 2026, after the July 2025 contract.
WK 26
MoneyDelivery
A portal update shows internal fit-out with electrical wiring still hanging. The portal date may be the upload date rather than the date the photograph was taken.
WK 27
DeliveryApprovalsRegulator
Two emails:
Company update: announces the QBCC licence and new pricing.
Shipping update: says the vessel failed to load before the Christmas shutdown; the buildings "must be positioned on the top of the ship with nothing loaded above them", and Chinese New Year is approaching.
WK 27
MoneyDeliveryRegulatorHealth
The first held express statement from Expandify that manufacture is complete arrives 90 days after Kay paid the Build Complete instalment.
Expandify, in an email addressed "Hello Deborah": "Your home has been completed." Chinese New Year is slowing shipping. Separately, the installation contractor has been terminated on quality grounds; shipment is expected “next month” (February), with arrival in late March and installation in late March or April.
Kay Power replies: "my name is Kay not Deborah. At least when delivering bad news you can get my name right... I have been living in a bedroom with minimum clothes and my stuff is in my daughter garage since July 2025 as I thought it be 6 mths".
The date of this email establishes when the held written confirmation was given, not the exact date manufacture was completed.
WK 28
Delivery
Clayton Bielby apologises for the wrong name and the delays and takes over as installation contact.
WK 32
DeliveryApprovals
The February shipment forecast passes; approval work is also unresolved. The 20 January email forecast shipment in February. The next written schedule, on 12 March, instead gives a 27 March departure. This is an outcome of the earlier forecast, not a separate February shipping update.
Expandify later dates its contact about septic requirements to the end of February and Sarah says it had been dealing with approvals since about February. Those accounts do not establish the date of a formal RFI. Clayton’s 8 May email identifies the certifier’s written information request as 20 March.
WK 34
Delivery
New schedule in writing: ship departs China 27 March, installation 4 May, handover 30 May.
WK 36
Approvals
Certifier requests four outstanding items. In his later 8 May email, Clayton identifies an information request from the certifier dated 20 March: designated parking on the site plan, Form 15 engineering, Home Warranty Insurance and a septic sufficiency report. He says the first three are within Expandify’s scope.
This is the date of the request as identified in that email, distinct from the company’s account of earlier discussions about septic requirements.
WK 37
Delivery
The 27 March departure moves to 13 April. A notice dated 27 March and attributed to OOCL says the scheduled China–Australia departure has been rescheduled to 13 April. It cites staff availability, fuel security and wider conditions. The notice is later supplied to Kay; its attribution has not been independently authenticated.
WK 37
MoneyDeliveryApprovalsRegulator
One Expandify email does four things.
Shipping: it attributes the delay to the Middle East conflict and Chinese fuel reserves, "outside of our control", and reassures Kay: "Your home is safe, secure, and held at port."
Licence: it announces the QBCC licence.
Contract: it requires all builds to be formalised under a replacement QBCC contract. The attached draft has a 241 day completion period from 29 May 2026.
Additional payment: it offers an optional accelerated pathway for an additional $26,880.36. This is not a compulsory extra charge to continue at the original price.
Why Alex takes over: Mum had been waiting patiently. By this point she was exhausted and devastated, and her GP had flagged stress-related health concerns. Alex says this email prompted her to take over dealing with the project. Her immediate priorities were to establish whether the home would reach Australia and what was happening with the approvals. This personal context is the family’s account, supplied by Alex, rather than a medical finding drawn from the correspondence.
Project week
DeliveryApprovalsRegulator
Alex checks the shipping explanation and replacement contract independently. In the carrier call, customer service says China–Australia services are continuing; it does not check Kay’s specific booking. In the QBCC call, Alex asks about licence timing and the proposed replacement contract and is directed to obtain independent advice.
These enquiries precede the later formal complaints. They do not establish that Kay’s particular shipment was unaffected by disruption.
From Alex’s notes of the call: early April 2026, carrier customer service and QBCC. Alex’s notes date the calls 1 or 2 April.
Order of priorities: Alex’s account is that shipping and approvals came first. Once the family had more confidence about shipping, they returned to the replacement contract and involved a solicitor to protect Kay’s position. The first solicitor’s letter was sent on 30 June.
WK 38
MoneyDeliveryApprovalsRegulator
Information request: Alex sends Expandify five written questions on approvals and shipping.
Home Warranty: QBCC cover is issued; premium $1,225.80.
WK 39
MoneyDeliveryApprovalsRegulator
Alex’s account of the 15 April conversation with Sarah Morrison.
Shipping: Sarah repeats the Middle East explanation. Alex says the carrier told her otherwise. Sarah does not dispute that and offers written confirmation from the shipping partner. No such confirmation is in the record.
Timeline: Sarah accepts Alex’s concern that the project has exceeded Expandify’s stated maximum timeline.
Approval and septic: Sarah confirms council is questioning the septic tank, a replacement could cost $18,000 to $20,000, and says approvals had not been a major priority while shipping was delayed.
Accelerated payment: Sarah explains that $26,880.36 buys queue position ahead of another customer. She estimates potentially 14–21 days saved, depending on port arrival and the start date, while saying the construction days could remain the same.
A revised replacement contract reduces the completion period to 97 days. Expandify’s later account dates an April submission of plans to the septic contractor to 15 April. Alex’s notes of her 29 May call with the septic contractor describe earlier draft work and follow-ups in 2025, then updated plans in April; this was not established as the first contact ever.
Alex’s conversation summary · Call 1 of 6
Approvals, septic risk and shipping delays
Sarah accepted that the project had exceeded Expandify’s stated 29-week maximum project timeline.
As at 15 April, council had still not granted building approval. Sarah said Expandify had been dealing with approvals since about February; Clayton’s later email identifies the formal certifier information request as dated 20 March Shipping update thread, April to May. Kay had by then paid $134,401.82 in contract instalments (Alex’s round figure on the call was $140,000), and Expandify said the dwelling had been built.
An unbudgeted septic cost had appeared:
Council was questioning whether the existing septic tank could take the additional dwelling. Sarah confirmed council could require a holding tank or an upgrade, at $18,000 to $20,000. Alex had understood from an earlier assessment that the tank was fine.
Alex challenged the shipping explanation:
Sarah attributed the delay to Middle East fuel supply preventing ships leaving Chinese ports. Alex told Sarah that she had contacted the carrier and challenged that explanation. Sarah offered to obtain further written confirmation from the shipping partner. This records their conversation, not independent carrier verification.
The 29-week guide position was accepted:
Sarah accepted that the project had exceeded Expandify’s stated 29-week maximum project timeline. The signed contract’s anticipated-delivery field is blank, so the guide is not presented here as a contractual delivery date.
The $26,880.36 upgrade buys queue position:
Sarah confirmed the accelerated option would move Kay ahead of other homes in the batch. On the time it would actually save, she corrected herself twice before settling on a possible 14 to 21 days, depending on port arrival and the start date. The construction days could remain the same.
Alex challenged the build sequence; the preliminary assessment confirms both approvals were required:
Alex put it repeatedly that construction and a six-figure payment should not have proceeded before council approval. Sarah argued the point at length, relying on complying development. Separately, the certifier’s preliminary assessment, obtained by Expandify two months before the sales agreement was signed, records that both a Building Approval and a Septic System Approval were required Preliminary assessment report. It does not resolve whether manufacture should have waited.
The tone of this call:
Sarah answered the questions put to her, conceded the timeline point, and undertook to send documents. The difficulties here are with the substance of the answers, not with the conduct of the call.
WK 41
ApprovalsDelivery
Alex chases the promised approval update. A reception call records Alex seeking an overdue response and an update she says Sarah expected by the end of the previous week. Sarah is unavailable; reception offers to pass on a message. A later voicemail again asks for an approval update and callback.
From Alex’s notes of the call: April 2026, Expandify reception and voicemail. The date range reflects Alex’s notes.
WK 41
Delivery
Another shipping booking: 13 May departure, 14 June arrival. The booking provides an 8 May wharf-receival target and 13 May departure, with estimated Brisbane arrival on 14 June. On 8 May Clayton confirms that the expected wharf receival will not happen.
WK 42
Approvals
The wastewater design remains the immediate approval task following the April submission of plans.
Expandify follows up with the septic contractor: 5, 11, 13 and 23 May.
The septic contractor's position: it is waiting for septic-tank data and is short staffed.
What this window establishes: during this stage, Expandify is the party pursuing the outstanding design information.
WK 43
DeliveryApprovalsMoney
“This is a delay on our end.” Clayton confirms that Kay’s home will not reach the wharf as expected that day. He attributes the hold to administrative and logistics items on Expandify’s side, says the home is built and ready, and accepts responsibility.
Missed reply: he apologises for not answering Alex’s 29 April email.
Next shipping commitment: a confirmed sailing-date update no later than 30 May.
Installation order: Kay is third in her batch, behind two other homes.
Approval commitment: an update on certification items within three business days, including the outstanding Form 18.
Contract position: he describes the sales agreement and proposed installation contract as covering separate scopes.
The later 18 May email acknowledges that the promised three-business-day update was not delivered.
WK 44
DeliveryApprovalsMoney
Questions remain unanswered; Clayton admits missing another update. On 14 May Alex asks for the specification sheet current at signing, the alleged unpaid plumbing invoice and an explanation of conflicting approval accounts. She challenges the assertion that the proposed contract covers a different scope.
On 18 May Clayton acknowledges that he missed the promised three-business-day certification update and did not answer the 14 May questions. He says:
the parking, engineering and insurance information has now been supplied to the certifier;
a formal septic report was not produced because the inspector had not been paid, and the invoice went directly to Kay;
the attached specification sheet is the version applicable when Kay signed;
a separate building contract “was always required”, but Kay is under no pressure to sign until comfortable.
The invoice and historical specification-sheet claims are subsequently challenged in the May and June records.
WK 44
Approvals
Form issued: the private certifier issues a Form 18 Notice of Engagement addressed to Kay as owner.
Property ownership: the land is owned by her daughter and son-in-law.
WK 45
ApprovalsMoney
Alex checks the approval and invoice accounts. Sarah reports chasing the Form 18 and tells the certifier to use Alex as the contact. Alex points out that the form names Kay as owner although the property belongs to her daughter and son-in-law.
Alex also reports being told that the plumbing invoice went to Expandify rather than Kay. That intermediate account is superseded on 29 May by the plumber’s direct clarification that no invoice had been issued; it should not be treated as the final invoice position.
WK 46
MoneyDeliveryApprovals
Alex, to three Expandify staff and copying the septic contractor: "it's become pretty clear that there was never an outstanding invoice from the septic contractor holding things up".
Invoice record: no such invoice has since been produced.
Design: the septic contractor delivers the final wastewater design.
The contractor’s direct account: in Alex’s notes of the call, the septic contractor's representative checks the job and says no invoice had yet been issued for the job. The call describes draft work and follow-ups to an earlier Expandify contact in 2025, followed by updated plans in April. The existing tank is described as adequate, with changes required to the land-application area. That assessment is not council approval.
Who will lodge: Expandify confirms in writing that it will complete the plumbing-permit submission.
From Alex’s notes of the call: 29 May 2026, the septic contractor. The statement about invoicing is the provider’s account, distinct from Alex’s earlier reported understanding.
WK 46
Delivery
Alex goes directly to the freight forwarder. The forwarder describes a check of container contents, held or cancelled bookings and a factory-side problem still awaiting resolution. He also describes earlier wider shipping disruption and confirms that Kay’s dwelling is a real identified order.
His account supports both company-side and external causes at different stages; it does not establish every cause or its duration.
From Alex’s notes of the call: 29 May 2026, freight forwarder. This is the forwarder’s account of the booking history.
WK 46
MoneyHealthDelivery
Sarah Morrison: "The hold up is on our end, and we are working hard to get it resolved."
Kay replies: "Not only financially but the stress of this has cause me health problems as well... I am getting more depressed each and every day".
Significance: the first health warning to the company in writing.
The promised sailing update: an update is sent, but it does not provide a confirmed departure. The 12 March programme had forecast handover by 30 May; the 1 June email confirms that none of the six homes has yet left China.
WK 46
MoneyHealthDelivery
Health and housing acknowledged: "The financial pressure, your health, not being able to stay with your daughter while she prepares for her baby. That is a lot to be carrying."
Batch position: "All six homes in your batch are in exactly the same position. Not one has left China yet".
WK 46
Delivery
Pickup authority and vessel space are still unresolved. The freight forwarder says he is awaiting the go-ahead to collect from the factory as well as shipping space. Alex asks how that fits with the repeated assurances that the home is built and ready.
From Alex’s notes of the call: 3 June 2026, freight forwarder. Alex’s notes distinguish factory pickup authority from the vessel booking.
WK 47
MoneyDeliveryRegulator
Alex’s account of the 8 June conversation with Clayton Bielby.
Delay: a materials testing error, followed by a $30,000 dispute with the factory, which Clayton attributes to the factory.
Program: booking that week, foundations in the first week of July and arrival in mid July. Alex’s contemporaneous 16 June email records her understanding as full installation and handover two to four weeks after arrival. This was an approximate programme, not a guaranteed mid-August handover date.
Payment position: asked about amounts already paid and the payment arrangements under the existing and proposed contracts, Clayton says he does not know and will refer it.
Family account: Alex says that, on the strength of that programme, she will tell Kay to hold off looking for a rental. The call records that intended advice, not when Kay acted on it.
Two further commitments: Clayton says Kay is now first in the batch, because another customer’s site-engineering delay has moved her forward. He also says a new contract will have to be signed; he says he had not realised Kay had not signed it.
He says the booking is being placed that week and describes the usual slot timing. Alex’s subsequent “on the water within a week” account appears in the 12–16 June records; it is distinguished there from his stated booking programme.
Alex’s conversation summary · Call 2 of 6
Shipping cause, overpayment and contract concerns
Clayton acknowledged that Expandify was new to the industry.
Participants: Alex, Kay's daughter and authorised representative. Clayton, Expandify (Expander Dwellings Pty Ltd). First contact between them.
Open complete call context +Close complete call context −
Alex’s summary of the conversation, with related evidence labelled separately.
Expandify gave a materially different shipping explanation:
In April, Expandify attributed the delay to Middle East fuel supply preventing ships leaving Chinese ports. In June, Clayton added a materially different cause: material declarations mis-recorded against the wrong containers and requiring retesting, plus a $30,000 dispute with the factory over who paid. The June account did not reconcile itself with the April account. The record does not establish whether both affected different periods.
Alex questioned the payment position before the formal complaint:
Alex questioned how the amounts already paid related to the existing and proposed payment arrangements and raised concerns about protection of the money. Clayton said he did not know and would refer the questions to Sarah and the company’s solicitor. This exchange does not determine a statutory overpayment.
Expandify was disengaging from the septic contractor:
Clayton said Expandify was disengaging from the septic contractor and did not want him working on its sites, while the septic assessment that gates the building approval was still sitting with that contractor.
Kay moved to first in the batch by chance, not by payment:
Clayton confirmed Kay was now first to be installed off batch 5, because another customer ahead of Kay hit a site delay. In April Sarah had offered that queue position for $26,880.36 Replacement contract proposal.
A timetable was given:
Clayton outlined the expected sequence: booking that week, foundations in the first week of July, arrival mid-July, two weeks for stage one, two weeks for trades, then certification and Form 21. These were forecasts, rather than confirmed completion dates.
An admission of inexperience:
Clayton acknowledged that Expandify was new to the industry.
The replacement contract was still being required:
Clayton said a new contract would have to be signed and that he had not realised Kay had not signed it. Later, on 9 July, Tim told Alex that installation could proceed without another signature Alex & Tim Austin · legal action and contract concerns · 9 July.
WK 48
Delivery
Alex checks the one-week shipping assurance. Alex tells the freight forwarder that Clayton had said the home would be “on the water within a week”. The forwarder says space is still being sought and describes vessel rollovers; he undertakes to check the booking.
Alex repeats the one-week account in her 16 June email. It is her contemporaneous account of Clayton’s assurance, not an exact quotation attributed to him from the 8 June conversation.
From Alex’s notes of the call: 12 June 2026, freight forwarder. The one-week statement is Alex’s own, repeating what Clayton had told her.
WK 48
DeliveryMoneyApprovals
Another proposed programme: 74 days from 9 July. Sarah sets out a 74-day programme for the proposed contract, starting with foundation installation on 9 July and excluding shipping days. She compares the existing agreement, proposed contract and current payment practice, says both contracts have the same payment terms and offers to address Alex’s concerns.
Clayton’s written recap also provides a revised shipping estimate, apologising that the recap was delayed while he was on site. These are proposed dates, not an agreed replacement contract.
WK 48
ApprovalsRegulator
Metadata challenge: the specification sheet produced as the pre-signing version was created 18 May 2026 and refers to QBCC Home Warranty Insurance, which post-dates the licence.
Records requested: the original spec sheet, the email that sent it.
WK 48
MoneyDelivery
Sarah Morrison revises the program in writing: "the booking we have obtained has an arrival of the 8th of August putting anticipated handover mid-September." The same email schedules foundations: "Foundations have been scheduled in for the 8th of July", with a foundations-team booking for the 9th, "dependent on approvals coming through". The email names Clayton's mid-July estimate and gives no cause for the slip.
Alex challenges the change: she asks how this fits with the previous week’s shipping assurance and how the foundation date remains achievable with plumbing and building approvals still outstanding. She questions the interval since Expandify accepted responsibility for the plumbing submission on 29 May.
Independent shipping explanation: Alex’s notes of her call with the freight forwarder that day record him explaining that the oversized/open-top cargo needs additional vessel space and describes peak-season constraints and blank sailings. He confirms the revised booking available to him. This explains the booking constraint at that stage, rather than all earlier delays.
From Alex’s notes of the call: 16 June 2026, freight forwarder. The written booking is separately held.
The illustrative handover window: Sarah’s table gives 14–18 September, but describes the table as “only an example” based on an ideal situation, not a guarantee, and subject to weather and labour events. The first date in the handover row is printed as 14/09/2025; the surrounding programme and 18/09/2026 end date indicate a year typo. The summary uses 14–18 September 2026 with those qualifications.
WK 48
Approvals
Sarah Morrison gives Expandify’s account of the earlier conversation.
Company's account: a 16 May 2025 conference call with Lauren, Clayton and Kay was specifically about the septic system.
Position asserted: Expandify says Kay was told septic sat outside its scope.
An actual plumbing invoice is issued: the septic contractor sends Kay INV-1575 for $600, saying Expandify directed it to invoice her and that Expandify will lodge the application. Alex forwards it referring to Clayton’s indication that Expandify would pay; Sarah later disputes that commitment. This invoice is distinct from the alleged earlier unpaid invoice said to have held up the report.
WK 50
Regulator
Metadata: "On the spec sheet metadata mixup, that one is on me."
Attachment: Sarah attaches a file called “Specification Sheet.pdf”. The attachment is byte-for-byte identical to the March 2025 brochure. It contains no septic or wastewater exclusion. That attachment does not establish what Kay received on 16 May 2025.
Scope: Sarah also relies on clause 15.11 of the signed contract.
WK 50
MoneyApprovalsRegulator
Why the family involves a solicitor: after investigating the shipping and approval problems, Alex says they had enough confidence about shipping to turn to the replacement contract. Given the delays, unresolved scope and payment questions, they wanted Kay protected and the issues resolved before arrival and the next payment.
Kay’s solicitor’s letter raises:
Unlicensed contracting under section 42(1) of the QBCC Act.
A 30 per cent deposit against a 20 per cent statutory cap under section 33(1)(c).
Progress claims untethered from progress at the site under section 34.
Misleading and deceptive conduct under section 18 of the Australian Consumer Law.
Subsequent correspondence: Kay’s solicitor’s 12 August letter records that the 30 June and 14 July letters had not received a response. The September entries below record the later exchanges between the solicitors.
The letter addresses the proposed replacement contract and the existing supply-and-install scope. These legal allegations are the solicitor’s positions, not findings by a regulator or court.
Affordable Modular Buildings: July 2026
AMB takes over installation; Alex seeks a program and follows up the promised conversation with Kay’s solicitor.
WK 50
Delivery
AMB partnership announced in writing. Expandify announces that Affordable Modular Buildings will support installation and project delivery, while Sarah and Clayton remain involved. The email promises a further introduction, followed by the 4 July call.
WK 51
DeliveryRegulator
New contractor: Expandify introduces Affordable Modular Buildings to take over installation.
Solicitor’s letter: Tim says he understands why Alex sought legal help and proposes discussing the scope and contract with the family’s solicitor.
Commitment: Tim says he wants to speak with the family's lawyer on Monday.
Project position: the buildings remain in China.
Kay's housing: Alex says Kay can no longer stay with her sister and will be moving into Alex’s home for the next few months. The call does not establish the actual moving date.
Tentative completion discussion: Tim raises early October while saying he does not yet have a full handle on the project. This is an initial estimate, not a confirmed handover commitment.
Tim's position on Alex's solicitor was the opposite of what it later became:
On this call Tim asked to speak to Kay’s lawyer, said he could see why Alex had taken that path, and discussed agreeing a scope of work with a proper contract. Five days later, he warned Alex that pursuing legal action would hold up the project, although he also suggested retaining the solicitor on the side Alex & Tim Austin · legal action and contract concerns · 9 July. Five weeks after this introductory call, he said having a legal person involved exposed him to risk and asked Alex to pull back her solicitor as a precondition of work continuing Alex & Tim Austin · withdrawal and payment dispute · 12 August.
The buildings were still in China:
Sarah confirmed the buildings were still in China waiting for their departure date. On 8 June Clayton had said the booking was being placed that week, with arrival mid-July and foundations in the first week of July. The buildings had not shipped and foundations had not begun; the mid-July arrival forecast was still ahead of the call date.
Affordable Modular Buildings was taking over installation for all Expandify clients:
Sarah’s stated reason was capacity: Tim had a much bigger team that could manage the builds more efficiently than Expandify could at its current size.
Tim confirmed Expandify remained the contracting party:
Asked directly whether Expandify still needed to be in the conversation, Tim confirmed that it did and described the mechanism as an amendment to the existing contract.
Tim cited different customer and project figures on different dates:
Alex confirmed Kay could no longer stay with Alex’s sister and would be moving in with Alex for the next few months. The timeline had kept changing.
WK 51
Delivery
Shipping booking revised a second time: estimated arrival 19 August.
WK 51
Regulator
Alex calls to follow up because neither she nor Kay’s lawyer has heard from Tim after his Saturday commitment to call on Monday.
Written update: Tim says AMB is onboarding Expandify’s projects into its management system.
Alex’s account of the conversation: Tim warns that legal action would delay the project and that he would stop talking to her. Later he suggests keeping the solicitor involved on the side and says a conversation is possible.
Contract: after Alex reads the agreement’s wording, Tim accepts her point. He says installation can proceed without another signature, differing from Clayton’s 8 June position.
Payment protection: Tim expresses concern about consumers’ exposure in modular projects; this is his account, not a determination of statutory cover.
Programme and shipping: Tim gives September as a tentative completion target and says the home is already on the water. The carrier record dates the first-leg departure from Xingang to 16 July; the available accounts do not resolve that difference.
Foundations: Alex’s written follow-up asks about the previously scheduled start. The 8/9 July booking had been conditional on approvals; later correspondence confirms work had not begun.
Alex’s conversation summary · Call 4 of 6
Pressure to drop legal action, and the contract concession
Five days after asking to meet Kay’s solicitor, Tim warned that pursuing legal action would stop work and communication and make the situation worse.
Participants: Alex, Kay's daughter and authorised representative. Tim Austin, Affordable Modular Buildings.
Open complete call context +Close complete call context −
Alex’s summary of the conversation, with related evidence labelled separately.
Tim pressed Alex to abandon legal action, 5 weeks before he withdrew:
Tim told Alex that pursuing legal action would waste time, energy and money, that he would have to stop work and stop talking to her, and that continuing down that path would hold up the project and make the situation worse. He framed this as friendly advice. Alex felt threatened and pressured to drop the legal action. She experienced the warning about stopping work as an attempt to intimidate her into stepping back from the legal protection she had sought for Kay. Later in the same call, Tim suggested retaining the solicitor on the side and said there was no problem having a conversation.
That was 5 days after Tim asked to meet Kay’s solicitor:
He conceded the contract point after Alex read it to him:
Tim first told Alex the contract did not say what Alex said it said. Alex read the wording to him. He then accepted her point and said Expandify probably should not have used that terminology. The wording discussed appears in the signed agreement Signed sales agreement · 11 July 2025.
The signed agreement still has a purchase-price placeholder:
Schedule 1 item 4 of the executed Sales Agreement reads "$###### as detailed in accepted build proposal". The placeholder was never replaced. The proposal pages in the same agreement total $224,003, so the price remains ascertainable.
He described his own position as subcontractor:
Tim said the contract was with Expandify, not with him or his entity, and presented that distinction as putting him clear of responsibility for the contract. This was his stated position; it does not determine his legal responsibilities.
He asked about approvals for the project he was taking over:
Tim asked Alex whether the project had approvals.
He said 95% of competitors' Class 1A claims are false:
In Alex’s account, Tim said that 95% of competitors’ Class 1A claims were false. This reports his assertion, not an established fact about those competitors. Expandify had told Alex in April that this dwelling was certified Class 1A. Tim’s general claim does not establish that Kay’s dwelling was non-compliant.
Tim said installation could proceed without another signature:
Alex asked whether installation could proceed without signing anything else. Tim confirmed that it could. This differs from the replacement-contract requirement repeated by Clayton on 8 June Alex & Clayton Bielby · shipping, payments and contract · 8 June.
WK 52
RegulatorDelivery
Alex asks QBCC about the available complaint routes. The officer distinguishes an offence complaint from Early Dispute Resolution, describes approximately four weeks for EDR contact and says the processes can be pursued separately. The call also refers to Alex’s earlier April enquiry.
This is advice about the processes, not a determination of the contract dispute or an instruction to stop work.
From Alex’s notes of the call: 10 July 2026, QBCC. The EDR timeframe is recorded in the notes.
WK 52
DeliveryApprovals
Three records move in parallel.
12 and 16 July: the first container gates in at Tianjin Xingang, then the vessel departs Xingang.
16 July, Tim Austin by email: "every Expandify project is being properly transferred into our AMB project management system... all project information, including documentation, approvals, variations, engineering, notes, and project history". No record of Kay's consent to that transfer is in the record.
The 16 July email also acknowledges an onboarding delay and promises further project information. The first sailing is from Xingang to Qingdao, not the final departure from China.
WK 52
MoneyDeliveryRegulator
The solicitor follows up. Kay’s solicitor sends a further letter after the 30 June demand. Its later letter of 12 August expressly records that neither the 30 June nor 14 July letter has received a response.
This is the unanswered legal-correspondence sequence; separate project updates continued during the same period.
WK 53
DeliveryApprovals
Shipping: Tim Austin says the building is on the water, with estimated port arrival 19 August.
Plumbing: "the plumbing has been approved".
Building approval: described as close, but held up by an engineering RFI with the certifier.
Elapsed time: the plumbing approval arrives roughly 14 months after Expandify's own report said one would be needed.
WK 54
Delivery
OOCL bill of lading tracking shows the cargo transhipped at Qingdao; the vessel departs Qingdao on 1 August, estimated arrival Brisbane 26 August.
28 July enquiry: the freight forwarder confirms the cargo’s arrival in Qingdao and attributes the revised timetable to high winds and wider shipping disruption. The later tracking record establishes the actual 1 August onward departure.
From Alex’s notes of the call: 28 July 2026, freight forwarder. The call distinguishes the first leg, transhipment and onward sailing.
WK 54
Delivery
Weekly updates and a programme promised. Tim’s written communication commitments include weekly updates, milestone/programme information and notices about foundations, installation, services, variations and payments. Alex’s later 10 August email requests a written programme from foundations to handover.
The regulator, the invoice and the call: August 2026
The August sequence: QBCC notice, early payment demand, written health instruction, calls and AMB’s withdrawal.
WK 55
Regulator
Authority: Kay appoints Alex as her representative.
Family-record lodgement date: QBCC offence complaint. The cited 4 August acknowledgement establishes the assessment status, not the precise submission time.
4 August status: assessed and placed in a queue pending allocation to an investigator.
Status caution: this is not a finding that an offence occurred.
WK 55
Regulator
Family-record lodgement date: QBCC Early Dispute Resolution request. The cited 10 August intake email does not independently establish this submission date.
10 August intake: QBCC says it will assess suitability and, if accepted, contact the parties within four weeks of lodgement.
Process: participation does not automatically result in an inspection.
WK 55
MoneyApprovals
Tim Austin reports: the building approval has been received - 391 days after the contract was signed.
His message: "I bet you feel better now :)"
Evidence held: the notification. On 12 August, the certifier supplied the approved building-approval document set directly to Alex.
The notification asks for no action: Tim’s email says no action is required at this stage. Alex later requests the decision notice and conditions, then obtains the approved set directly from the certifier on 12 August.
Publication source: The published building-approval document is a labelled extract of the decision, conditions and related forms; the complete original remains private.
WK 56
MoneyDeliveryRegulator
Invoice: INV-0278 - $67,200.91, "30% Arrival in Port Progress Payment".
Dates: due 14 August; the invoice itself says "Expected arrival date is 21st of August".
Claim terms: framed under the Building Industry Fairness (Security of Payment) Act 2017, with 12 per cent per annum interest on late payment.
Effect if paid: Kay would reach $201,602.73 - 90 per cent of the price - before the dwelling reaches Australia.
WK 56
MoneyDeliveryApprovalsRegulatorHealth
3 threads pass through this eventExplore the related exchanges
1:57pm. The QBCC emails both parties acknowledging the EDR request. Participation "does not automatically result in a building inspection"; officers do not "assess building work or determine fault"; if accepted, contact within four weeks of lodgement.
6:25pm. Tim Austin emails Kay and Alex querying the EDR: "I am confused. I just got you a building approval and I am working as the contractor to deliver your work. Are you still not happy with my efforts?" He requests an urgent phone call.
7:14pm. Alex replies, confirms the EDR concerns the contract with Expandify and that neither Tim nor AMB was named as respondent, and says she is happy to find a suitable time to speak. She asks Tim to propose a time and give a brief outline of the matters he wants to discuss.
8:28pm. Tim Austin forwards Expandify's invoice: "Please make this payment promptly and send me a payment remittance to my email".
9:31pm. Alex explains the contractual arrival milestone and writes: “Kay is not refusing to meet her payment obligations.” She disputes the 14 August deadline, asks for a written program from foundations to handover, and gives the health instruction: "Kay is undergoing cardiac investigations following significant stress associated with this project. Please direct all future correspondence to me and do not copy Kay".
Payment timing: the forwarded demand seeks $67,200.91 and was sent 74 minutes after Alex’s 7:14pm explanation, or 6 hours 31 minutes after the QBCC notification. The invoice is dated 9 August, before that notification, and states a 14 August due date. Expandify had described billing ahead of port arrival in October. This sequence does not establish that the complaint caused the invoice to be created.
“Please make this payment promptly and send me a payment remittance to my email.”
“Please direct all future correspondence to me and do not copy Kay.”
WK 56
MoneyDeliveryHealthRegulator
A call with Alex had already been offered. Tim requested an urgent call at 6:25pm the previous evening. Alex replied at 7:14pm offering to find a suitable time and asking him to propose one.
11:10am · AMB’s projects team acknowledges the email. The team identifies the payment milestone and invoice dispute, says the email is going to Tim as urgent, and confirms that the request about future correspondence has been noted and will be brought to his attention.
Alex follows up. Still waiting for a response, she asks for the approval notice and conditions, referring to the disputed invoice, lack of a foundation date and her earlier offer to speak. The quoted copies show different header times; her text says it is now 2.00pm.
About 3:10pm · Tim calls Kay, according to Alex’s recollection of the time. Kay’s signed same-day account places the call in the afternoon without an exact time. She says he initially asked for Alex’s number, then spoke at length about the project and payment. She describes pressure to pay early, warnings that she could lose her money, four clients with lawyers “kicking up a stink”, and his statement that he could “pull the plug”.
Kay’s account of the impact: “By the end of the call I was crying, frightened and panicked... I was terrified that I might lose both my home and the money I had already paid”.
3:31pm · Tim emails Alex: “Please call me … we need to talk.” The email follows the call to Kay on the timing Alex recalls.
3:50pm · Tim sets out conditions for continued involvement. He says he became involved so customers do not “potentially lose your money if Expandify can’t continue”. He asks Alex to follow his team’s directions, including payments “when due”, or he will reconsider AMB’s involvement.
The contact instruction was already in writing. Alex’s 10 August email disputed early payment and directed future correspondence to her because Kay was undergoing cardiac investigations. AMB acknowledged it before the call.
Nominee search: the QBCC register search dated this day shows an active company licence but no current nominee. It does not give the previous nominee’s departure date or the date QBCC was notified. Those dates and the identity of a replacement are subsequently requested.
“I've also noted your request regarding future correspondence and will ensure this is brought to Tim's attention for handling moving forward.”
“I was terrified that I might lose both my home and the money I had already paid.”
August: licensing and payment pressure
WK 56
Regulator
Clayton Bielby is the current director in the 11 August extract. Sarah Kay Morrison and Lauren Zita Leidig are previous directors, with recorded cessation dates of 31 March 2026. Lauren’s secretary role also ceased on that date. The complete original is held privately; a redacted officeholder excerpt is published.
“I've also noted your request regarding future correspondence and will ensure this is brought to Tim's attention for handling moving forward.”
“I was terrified that I might lose both my home and the money I had already paid.”
The regulator, the invoice and the call: August 2026
The August sequence: QBCC notice, early payment demand, written health instruction, calls and AMB’s withdrawal.
WK 56
ApprovalsRegulator
3 threads pass through this eventExplore the related exchanges
Alex returns Tim Austin’s requested call at 1:14pm. This is Alex’s account of the conversation.
Payment: Tim says the next instalment funds pickup, transport, inbound import costs and onsite work. Alex repeatedly distinguishes the early deadline from refusing payment. When Tim says her email refused payment, she corrects him and points back to the arrival milestone. Her 10 August email had expressly made that distinction, and her 11 August follow-up again referred to the disputed invoice.
Withdrawal and financial concerns: Tim initially says AMB is considering ending its service contracts and discussing that position with Expandify. Later he says AMB is withdrawing. He describes Expandify operating on a limited budget and warns that continued pressure could leave clients out of pocket. These are his statements; they do not establish insolvency.
The call to Kay: Alex challenges the contact despite her written health instruction. Tim says his client workload makes it difficult to remember individual circumstances and says he apologised to Kay. Tim says he apologised; his account was already included on this website. Later clarification, relayed by Alex on 29 September 2026: Kay maintains that he did not. Her original signed account is unchanged..
Regulatory and legal involvement: Tim asks Alex to pull back the QBCC matter and her solicitor as a precondition of continuing work. He describes a 13-week delay and an inspection. QBCC’s written advice instead describes no automatic inspection and contact within four weeks if the request is accepted; it does not establish AMB’s own policy on pausing work.
Why Tim said AMB might pull out: In Alex’s account, Tim links AMB potentially withdrawing to clients, including Alex, not following his direction about solicitor and QBCC involvement. He asks Alex to pull back both. Alex responds that each person is responsible for their behaviour and communication, and that she would never treat his parents as he treated Kay.
Related written evidence: Kay had paid $134,401.82 in contract instalments (60%); the October entry explains the paid invoice’s allocations. Expandify later confirmed AMB’s departure on 19 August.
Also that day: Kay’s solicitor writes to Tim and Expandify; the certifier supplies the approved building-approval documents.
Contact disputed: Tim says he called and texted Alex after speaking to Kay; Alex says she has no record of either, and he offers to send proof. No records resolving that disagreement are identified.
The solicitor’s unanswered requests: the 12 August letter records no response to the 30 June and 14 July letters. It requests written authority for Tim’s role, licensing/nominee and approval information, a foundation start date and evidence addressing the stated financial concerns, with a response requested by 4 pm on 14 August.
Further follow-up: Alex’s private reception/certifier calls document attempts to reach Tim and obtain the approval set; the short certifier callback itself only promises to check. The written document supply is separately recorded. An automated due-soon reminder for INV-0278 is also sent to Kay, distinct from the later overdue reminder.
Publication source: The published building-approval document is a labelled extract of the decision, conditions and related forms; the complete original remains private.
Reason given for the call: In Alex’s account, Tim said he called Kay to find out why payment would not be made. Kay’s signed account records that he initially said he wanted Alex’s number, then discussed the project and payment at length.
Alex’s conversation summary · Call 6 of 6
Tim Austin says Affordable Modular Buildings is out of Expandify projects
Tim announced AMB’s withdrawal and blamed Alex for continuing the QBCC matter. Alex challenged the early payment demand, the call to Kay and the pressure to withdraw regulatory and legal involvement. Expandify later confirmed AMB’s departure on 19 August. The later payment and trust proposals are in Expandify’s company record.
Participants: Alex, Kay's daughter and authorised representative. Tim Austin, Affordable Modular Buildings.
Open complete call context +Close complete call context −
Alex’s summary of the conversation, with related evidence labelled separately.
What Tim Austin said Affordable Modular Buildings was doing:
Tim Austin said Affordable Modular Buildings was considering terminating its contracts of services, was still discussing the position with Expandify that day and the next, and then said Affordable Modular Buildings had completely withdrawn and was out. He said Kay’s build would still be completed by Expandify rather than Affordable Modular Buildings. Expandify later confirmed the departure on 19 August Expandify announces Affordable Modular Buildings’ departure · 19 August. The contract between the two companies, and any withdrawal notice between them, are not in the record.
The call to Kay:
The payment dispute and the request to direct all future correspondence to Alex and not copy Kay were in the same email to Tim Alex’s payment dispute and health instruction · 10 August. Affordable Modular Buildings acknowledged the direction the next morning Affordable Modular Buildings acknowledges Alex’s contact instruction · 11 August. Tim called Kay that afternoon, then directed Alex back to that email when defending the payment issue. Kay’s signed account says he told her he was calling to get Alex’s number Kay & Tim Austin · payment pressure · 11 August signed account. Tim said the next day that he called to find out why the payment would not be made and that he apologised to Kay at the end of the call. Kay’s signed same-day account records no apology; that omission does not establish that none was made. Tim also said he called and texted Alex and offered to send the records; Alex said she had no record of either. No records resolving that dispute are in the record. His explanation that he had 188 clients does not explain why the written instruction was not followed. The record cannot establish what he remembered before the call.
What Tim said Alex had done, and how she answered:
Tim placed Alex among a small group of clients he blamed for the decision. Alex answered that the only issue she had raised with Affordable Modular Buildings was an invoice due before the contractual arrival milestone and issued without a project programme. Tim pointed first to the progress payment; Alex answered that it would be due when the dwelling arrived. He then said a response about the building approval was missing; Alex asked what response had been required. Tim returned to payment and said her email refused it; Alex corrected him that she had disputed when it was due, rather than refusing ever to pay. The exchange then moved into his demand that she trust his expertise. Later, when Tim compared them, Alex said she would never contact his parents against a written health instruction. She said trust was built through accurate records and feedback and challenged how he managed his emotions when speaking to vulnerable customers. Tim later acknowledged that Alex had been badly let down and that the fault was probably not hers. By the end of the call, however, he blamed her for continuing the QBCC matter. Alex answered that each person remained responsible for their own behaviour and communication.
The invoice:
The $67,200.91 invoice was issued before the contractual arrival milestone and was due 12 days before the carrier’s then-estimated Brisbane arrival date [Arrival invoice · 9 August, Carrier tracking · 11 August]. Tim forwarded it 74 minutes after Alex had replied conciliatorily and offered a call, on the same evening QBCC notified both parties of the dispute request lodged for Kay; the invoice itself predated that notification [Alex explains the QBCC dispute · 10 August, Tim’s early payment request · 10 August, QBCC’s written advice]. Tim denied any connection between the payment demand and regulatory involvement. By then Kay had paid two contract instalments totalling $134,401.82, or 60 per cent [Paid deposit invoice · July 2025, Paid Build Complete invoice · October 2025]. Both paid invoices list the complete scope; the October invoice allocates amounts within its 30 per cent total to foundation and building installation, installation management, crane hire and delivery from port. Those allocations do not establish separate payment in full for each item. During the call Tim said the next instalment funded inbound import costs, transport, pickup and onsite work and asked Alex to trust his expertise. He also said he became involved so another business would not go under, described Expandify as having reduced operations to the owner and a very limited budget, and warned that continued pressure could leave clients out of pocket. Kay’s separate signed account records the more explicit warning that Expandify could not afford port costs and might go under Kay & Tim Austin · payment pressure · 11 August signed account. The record holds no company financial records, does not establish insolvency and does not establish whether Tim had reviewed the contract and earlier invoices before directing payment.
The pressure to withdraw the complaint:
Tim asked Alex to stand down Kay’s QBCC complaint and the family’s solicitor as a precondition of work continuing. He said all work should stop, an inspector would become involved after 13 weeks and the project would therefore be delayed. QBCC’s written advice, supplied two days earlier, instead described contact within four weeks if the request was accepted and said participation did not automatically result in an inspection QBCC’s written advice. It does not establish Affordable Modular Buildings’ own policy on pausing work.
WK 57
MoneyDeliveryRegulator
Invoice due: INV-0278 falls due under its own terms.
Timing: seven days before the arrival date printed on it; twelve days before the carrier's estimate.
Status: disputed and unpaid.
Elapsed time: week 57 against a maximum 29-week guide.
Where it stands: 16 August 2026
As at 16 August: the disputed invoice is marked overdue before the arrival milestone, with interest threatened.
WK 57
MoneyDeliveryApprovalsRegulator
Position as at 15 August:
Paid: $142,433.02, including 60% of the contract price.
Home and site: the dwelling remained offshore; no foundations or physical construction had begun at the property.
Contractor: Tim had said AMB was out on 12 August. The family had not yet received written confirmation or advice about who would complete the work.
Program and payment: no updated programme answering Alex’s 10 August request is identified in the reviewed record; Sarah had supplied a written programme on 16 June; the arrival invoice remained disputed and unpaid.
Regulator: the offence complaint was queued pending allocation to an investigator; the separate EDR request was in intake.
Solicitor’s letters: Kay’s solicitor’s 12 August letter recorded that its 30 June and 14 July letters had not received a response.
WK 57
MoneyDeliveryRegulator
6:15am, Expandify Accounts: an automated Xero reminder sent to Kay marks the disputed INV-0278 for $67,200.91 as overdue, two days after the invoice's stated due date, and asks for payment as soon as possible.
Interest warning: the reminder says bills more than seven days overdue will incur "12% interest charged daily". It does not add interest to the displayed $67,200.91 balance.
Three formulations: the signed agreement says 12 per cent per annum, compounded daily, from the day after a valid due date; the invoice says 12 per cent per annum, calculated daily, once payment is more than seven days overdue; the reminder omits "per annum".
Dispute remains: Alex's 10 August email said the contractual arrival milestone had not occurred, disputed the due date and asked for the invoice to be withdrawn or corrected. The automated reminder does not address that dispute.
Physical position: the dwelling remains offshore and no physical construction has begun onsite. The later tracking update appears under 18 August.
Late August: responsibility and foundations
Expandify resumes order management, Alex requests EDR closure, and the later records report port arrival and foundation work.
WK 57
Delivery
The freight forwarder offers reassurance. In Alex’s notes of the call, the forwarder expresses confidence in the freight position and describes the process for moving containers through a quarantine depot before delivery. He also describes control of the containers as a protection.
These are his explanations and assurances, not audited company finances or confirmation that installation will be completed. They sit alongside, rather than erase, the earlier concerns about payment and completion.
From Alex’s notes of the call: 17 August 2026, freight forwarder. The reassurance concerns freight and delivery arrangements.
WK 57
Delivery
Carrier tracking update. The capture gives an estimated Brisbane arrival of 30 August, revised from 26 August. This is a port-arrival estimate, not a date for delivery to the property or handover.
WK 57
Delivery
AMB no longer involved. Expandify tells Kay that communication and order management have returned to Expandify, effective immediately. It promises a personal order update within seven days. This is the written confirmation missing from the earlier August record.
WK 59
Delivery
Foundation booking and access. Expandify books Monday 31 August. Its next-day reply estimates five to eight hours, confirms excavator access and says Clayton will assess access for container delivery. It gives a port ETA of 30 August and says further timeframes will follow quarantine release. These are a booking and estimates, not certification of completed work.
WK 59
Regulator
EDR closed at Alex’s request after Expandify engaged. Alex explains that she asked QBCC to close the Early Dispute Resolution matter because Expandify had finally engaged with the family. QBCC’s 28 August email confirms the closure.
The reason for the request is Alex’s account; the closure email does not set it out. Closure was not a finding that the project dispute had been resolved or that the complaint lacked merit. The separate offence-complaint referral is a different process; this email does not report its outcome.
Engagement has resumed: by this point the family reports renewed engagement and requests EDR closure. The subsequent August/September solicitor exchanges must not be described as continued total silence.
September: the breach notice
The solicitors exchange delivery proposals, payment terms and a notice to remedy breach.
WK 59
Delivery
Port arrival reported; foundation work begins. The 1 September open letter records Expandify’s report of arrival at the Australian port on 30 August and acknowledges foundation work. The project record dates commencement to 31 August. Neither reported arrival nor commencement establishes completed foundations, site delivery or occupation.
WK 59
Money
Overdue email and attached invoice. The native email at 12:04:57 AEST states payment was due 30 August. Its attached INV-0278 retains issue date 9 August, now shows due date 30 August and still states expected arrival 21 August. The earlier version had due date 14 August. The later Xero screenshot records a separate 30 August send; this native email does not prove receipt of that earlier send.
WK 59
MoneyDelivery
Expandify’s solicitor writes on arrival, payment and title. The 12:47pm email reports arrival at the Australian port on 30 August and seeks the next $67,200.91 before release, delivery and placement. It says foundation preparation is underway, acknowledges that Expandify is securing a new nominee, and maintains that preparatory work can lawfully proceed meanwhile.
Title proposal: the email offers to transfer ownership on payment of this instalment rather than after full payment. This is an offer, not a completed transfer.
Timing of engagement: this email comes 62 days after the family’s solicitor first wrote on 30 June. The 12 August letter records the June and July letters as unanswered. Project updates continued, and by 28 August Alex reported renewed engagement and requested EDR closure. The record therefore supports delayed answers to the legal issues, not two months without any contact or a claim that 31 August was necessarily the first solicitor contact.
WK 59
MoneyDelivery
Kay’s solicitor writes on payment and completion. The open 1 September letter addresses payment timing, nominee details and completion. Kay’s solicitor asks when the previous nominee’s relationship with Expandify ended and when a new nominee will be appointed. It argues that the arrival instalment is due on 7 September, questions storage charges and requests a construction programme and handover date.
WK 59
MoneyDelivery
Separate regulator enquiry: in a private QBCC call, Alex asks when Expandify’s nominee ceased. The contact-centre officer cannot provide that date. They discuss contacting the EDR officer about reopening the recently closed matter; this call does not establish that it was reopened or that the licence was suspended.
From Alex’s notes of the call: 3 September 2026, QBCC. The entry records the enquiry and its limits, not a licensing finding.
WK 59
MoneyRegulatorDelivery
Kay’s solicitor responds on the nominee, the invoice and the delay. At 4:46pm Kay’s solicitor answers on the nominee position, invoice timing and Expandify’s explanation for the delay.
The 28-day calculation: the solicitor’s email identifies 8 September as the potential end of the period, expressly assuming 11 August was when Expandify notified QBCC of its nominee’s resignation. It follows up the 1 September questions, asking when the previous nominee resigned, who Expandify intends to appoint and when. The notification date remains unconfirmed.
WK 60
DeliveryRegulator
Notice to remedy breach. Kay’s solicitor states that his searches indicate Expandify has had no nominee since at least 11 August. He requires Expandify to appoint a nominee and advise Kay of their identity within 14 days of the letter, installation to start by 21 September and practical completion by 16 October. The notice states an intention to terminate if the requirements are not met; no termination is established by this notice. These are Kay’s solicitor’s stated positions and requirements.
QBCC search. The 4 September search again shows no current nominee, as did the first search on 11 August. The company licence is listed as active.
WK 60
DeliveryMoney
Expandify’s solicitor sets out its contract position and a conditional timetable. In its 4 September email, Expandify described the agreement as a goods-supply arrangement and said a separate building contract remained unsigned. It attributed delays to batch scheduling, factory shutdowns, packing and shipping disruption, including the conflict in Iran.
The company put the original batch delivery window between 10 December 2025 and 25 January 2026. It accepted 7 September as the payment date but sought cleared funds by 4 September for possible delivery on 8 September. With Kay third in the installation sequence, it estimated installation around 26 October and completion around 30 November, subject to payment, weather and third-party availability.
Kay’s solicitor disputed the contract interpretation and delay explanations in his response that afternoon. The incoming email dated the replacement contract to January, while the reviewed replacement-contract documents are dated April.
Installation position changes: Clayton described Kay as third on 8 May, then first on 8 June because another customer had a site delay. This timetable places her third again. The reviewed records do not explain that return to third place.
Historical dates differ: Sarah’s 8 October 2025 email dates the batch closure to 25 July; this solicitor’s account uses 4 August. Both are retained as attributed accounts rather than silently treating them as the same date.
WK 60
MoneyDeliveryRegulator
Kay’s solicitor’s sent response. At 3:55pm Kay’s solicitor replies that the contract “expressly states that it is for the ‘complete supply, install and council approval package’”, challenges payment of 90 per cent before the home is delivered and installed, and states his view that the work still to be done is worth more than the final 10 per cent. He records that Expandify’s representative told Kay that if she did not pay now she would not receive her home and Expandify would enter insolvency, and that the nominee position remains unanswered. The notice to remedy breach is attached. These are Kay’s solicitor’s positions, not findings.
WK 60
MoneyRegulator
Expandify issues a breach notice. Sarah Morrison relies on clauses 5.3 and 12.1, states the invoice was due on 30 August and gives 14 September as the remedy deadline. The notice says Expandify may terminate. Expandify’s solicitor later gives different dates: 7 September for payment and 15 September to remedy. These are the parties’ stated dates; the record does not determine which calculation is legally valid.
Twenty-eight days since our first search showed no current nominee. The 11 August search showed none, and the 4 September search again showed none. Kay’s solicitor had requested the previous nominee’s departure date and the identity and appointment date of a replacement. His 3 September email identified today as the potential end of the 28-day period, assuming Expandify notified QBCC on 11 August; the notification date remained unconfirmed.
Late September: payment and termination
The solicitors exchange proposals and notices. Alex’s 20 September update confirms foundations installed, with delivery and dwelling installation still to come.
WK 61
Money
Xero invoice-history screenshot. The capture supplied with Expandify’s solicitor’s later email shows INV-0278 for $67,200.91 and an AEST history entry recording a send to Kay on 30 August at 12:04 pm, plus later sends on 1 and 6 September and a reminder on 13 September. It is a sender-side record, not proof of receipt. The visible record-payment form has not been submitted and does not establish payment.
WK 61
MoneyRegulatorDelivery
Expandify’s solicitor demands direct payment and threatens termination. The 16 September email required the full instalment to be paid directly to Expandify before delivery and maintained that the company could complete the agreement. Citing a Xero send-history screenshot, it said the invoice had been sent on 30 August, payment was due on 7 September and the remedy period ended on 15 September. It set a final payment deadline of 3 pm on 18 September and threatened termination if payment was not received.
QBCC register: the search again shows no current nominee. The company licence is listed as active.
Kay’s solicitor disputed the invoice history and entitlement to terminate, and reiterated the proposed trust payment in his 18 September response. The send-history screenshot does not establish receipt, and this correspondence records a termination threat rather than an issued notice.
WK 62
MoneyRegulatorDelivery
Kay’s solicitor disputes termination and repeats the trust offer. The sent response challenges Expandify’s ability to perform and its right to terminate, raises nominee and contract issues, and reiterates the offer to pay the full $67,200.91 instalment into Expandify’s solicitor’s trust account on the proposed terms. No accepted trust arrangement is recorded.
We asked who would supervise Mum’s build. We still had no name. Our solicitor requested the nominee details, followed up and issued a formal notice. In his sent response on 18 September, he records that Expandify has yet to respond to the 4 September notice about appointing a nominee and advising Kay of their name.
Invoice dispute: Kay’s solicitor acknowledges notice of arrival on 31 August but disputes receipt of an invoice on 30 August. The 31 August overdue email, revised invoice and Xero send history are separate records; they do not establish receipt of the earlier email or payment.
QBCC register: still no current nominee listed, 38 days after the first search. Searches on 11 August, 4 September, 16 September and 18 September each show no current nominee. The company licence is still listed as active. The 18 September search also shows one structural rectification direction marked not complied with. The underlying property is not identified; this entry cannot be attributed to Kay’s home. No further payment or actual termination notice is confirmed in the reviewed record. These are the parties’ positions and register entries, not adjudicated findings.
Register detail: Page 4 records one structural direction to rectify marked “not complied”. The report does not identify the property or defects or connect the direction to Kay’s project. This is an editorial addition about the dated search.
WK 62
Delivery
Family update: arrived in Australia, foundations installed, home still undelivered. Alex confirms that the home has arrived in Australia and the foundations are installed. Delivery to the property, dwelling installation and a home Kay can occupy remain outstanding. This is the family’s update on 20 September, not the date of foundation completion or independent certification.
Current location unconfirmed: in the family call that day, Alex says she does not know whether the containers remain on the dock or have been moved to another holding location. Reported port arrival does not establish their location three weeks later.
From Alex’s notes of the call: 20 September 2026, family record. The uncertainty about location is recorded in the notes.
The unresolved position: the full-instalment trust proposal has not been accepted in the reviewed correspondence; Expandify’s solicitor demands direct payment and has threatened termination. The nominee departure/notification dates and replacement details remain unresolved. Kay’s solicitor disputes the right to terminate. No actual termination or further payment is confirmed.
September: payment dispute and register updates
WK 63
Regulator
QBCC company search, created at 12:50:57. The report lists:
Licence: Active, Builder – Open.
Nominee: No current nominee.
Direction to rectify: One structural direction marked “not complied”, the same count and category shown on 18 September.
The search does not identify the property, defects or compliance deadline, or connect the direction to Kay’s project. The separate disciplinary-action field records none. This is the search date, not the order’s issue date.
WK 63
MoneyHealth
Tim Austin’s response, captured 29 September. Tim disputes Alex’s account as false and potentially defamatory and says he has referred it to his solicitor. His principal response is preserved.
The call: He says he was explaining the payment and installation position. His response does not address Alex’s instruction to direct future contact to her because of Kay’s health.
Withdrawal: He says Expandify could not pay AMB for installation after the customer’s progress payment was not made, and that he warned Alex before withdrawing.
Other unpaid work: He also says Expandify owes AMB for other installation support. The underlying accounts are not held here; this does not establish insolvency.
Apology disputed: Tim says he apologised. In a separate clarification relayed by Alex today, Kay says he did not. Her original signed account is unchanged.
Alex’s supplied reply explains that her complaint concerns conduct during AMB’s involvement. She acknowledges that other customers can have good experiences.
Expandify’s website, observed today: It advertises trade supply through partners who deliver and install, and provides an existing-customer warranty/service contact. This does not establish when the wording changed or that Kay’s contract changed. Read the company website.
October: breach notice and public correspondence
WK 63
Correspondence
The letter demanded removal of the publications, undertakings, preservation of records and a response by 4 pm on 7 October. These are allegations and demands, not findings.
WK 63
Response
Tim defends his account. Alex replies. Tim Austin posted a defence of his conduct and Affordable Modular Buildings’ position on Facebook. Alex responded, challenging his account.
WK 64
Correspondence
Payment demanded by 12 October. Termination threatened for the 13th. Expandify’s solicitors demand $67,200.91 for invoice 0278. They adopt 18 September as the invoice issue date for this notice while maintaining that an earlier dispatch occurred.
The website and posts challenged. Expandify’s solicitors said they may contain defamatory imputations, urged that the website be closed and public posts stop, and said they would seek instructions before issuing a Concerns Notice. These are their allegations, not findings.
WK 64
Correspondence
The family’s solicitor refutes the allegations. The response requests further particulars and clarification of AMB’s QBCC licensing position, following an earlier request in August.
WK 64
Correspondence
Updated Google owner reply saved. It disputes the statements as false and defamatory and refers to the cease-and-desist letter.
The earlier apology and later reply are preserved alongside Alex’s review. This is a capture date, not a verified publication date.
October: termination and disputed entitlement
WK 65
RegulatorDelivery
Sixth QBCC search: still no current nominee. The company licence is listed as Active. All six searches, from 11 August to 12 October, show no current nominee. They are dated snapshots, not proof of continuous absence between searches.
One structural direction marked “not complied”. The report does not identify the property or link it to Kay’s project.
WK 65
MoneyDeliveryRegulator
Kay’s solicitor warns against termination. The sent open letter says any purported termination would be treated as repudiation. It was sent before the next day’s termination.
The solicitor’s grounds: no nominee, payment sought for work already paid for and/or site work not done, and breaches raised on 4 September still unremedied. These are Kay’s solicitor’s positions.
WK 65
MoneyDelivery
Expandify terminates Kay’s contract, effective immediately. Its notice relies on alleged non-payment of invoice 0278 for $67,200.91, following the 2 October demand. Kay disputes its entitlement to terminate.
No delivery. Resale and deductions proposed. Expandify says it will sell the home to another party, retain payments against its claimed costs and resale losses, and refund any balance.
No sale price, itemised deductions, refund amount or payment date is stated.