Email Sarah to Alex: booking rev1 attached + septic contractor chain 23-29 May (deep thread)
Source date: 16 June 2026 · Email thread print
Expandify’s revised June schedule gives August arrival and September handover estimates, with July foundation work dependent on approvals.
Sarah Morrison's written 16 June 2026 program revision recording an 8 August arrival, anticipated mid-September handover, foundations scheduled for 8 July and a foundations-team booking for 9 July dependent on approvals.
Source limitations
Publication copy with third-party identifying details redacted. The complete original is preserved privately.